SECTION 01025
<br />MEASUREMENT AND PAYMENT
<br />PART 1— GENERAL
<br />1.01 GENERAL
<br />Measurement and payment will be based upon work completed and accepted in
<br />accordance with the Contract Documents. No separate payment will be made for
<br />excavation, trenching, dewatering, M.O.T., backfilling, grading restoration, grassing,
<br />paving, testing (leakage, pressure, bacteriological sample points, soil
<br />compaction/density), or other incidental items of work not shown in the Agreement.
<br />1.02 EQUIPMENT AND MATERIALS IN STORAGE
<br />Partial payment for materials and equipment in proper storage at the site of the
<br />work or other approved storage site will not be made.
<br />1.03 MEASUREMENT
<br />A. Mobilization:
<br />Measurement shall be on a lump sum basis, and shall be limited to
<br />the following maximum amounts:
<br />ORIGINAL
<br />CONTRACT AMOUNT ISI_
<br />MAXIMUM_AMDllNI OF
<br />ROM MORE THAN
<br />TO AND INCLUDING
<br />ITEM FOR MOBILIZATION
<br />0
<br />100,000
<br />3,000
<br />100,000
<br />500,000
<br />15,000
<br />500,000
<br />1,000,000
<br />30,000
<br />1,000,000
<br />2,000,000
<br />60,000
<br />2,000,000
<br />3,000,000
<br />90,000
<br />3,000,000
<br />4,000,000
<br />120,000
<br />4,000,000
<br />5,000,000
<br />125,000
<br />5,000,000
<br />6,000,000
<br />150,000
<br />6,000,000
<br />7,000,000
<br />175,000
<br />7,000,000
<br />10,000,000
<br />200,000
<br />10,000,000
<br />-------------
<br />250,000
<br />Should the lump sum price bid for the item Mobilization exceed the maximum
<br />permissible amount for this item, as specified herein, the bid price will be reduced
<br />to the maximum permissible amount, and the reduced price will be used in correctly
<br />determining the total price for comparison of bids received. The cost of video -
<br />taping the pre -construction condition shall be included in the lump -sum cost of
<br />mobilization.
<br />B. Pipe: Measurement of pipe shall be computed using linear feet, as measured along
<br />the centerline of the pipe installed (Except when included in lump sum bid items-
<br />i.e.; Aerial crossing). No deduction will be made for the length of valves and fittings
<br />installed in the line. Where the measurement terminates at a valve, bend, tee, or
<br />01025-1