other fitting, the centerline of the valve or fitting shall be the point of termination.
<br />All required clearing, excavation, backfill, compaction, all restoration and
<br />replacement, M.O.T., paving, grading, density testing, pressure and BAC -T testing,
<br />pipe lining, coating, encasement material, restraining devices, and all mechanical
<br />joint fittings and thrust blocks shall be included in the unit price bid for the utility
<br />main.
<br />C. Fittings: The cost of all cast iron and ductile iron fittings and bolts, glands, restainers
<br />(megalugs), etc) shall be included in the unit price bid for the utility main.
<br />D. Gate Valves, air release valves, Tapping Sleeve and Valves, line stops and Other
<br />Miscellaneous Appurtenances: Measurement shall be on the basis of furnishing and
<br />installing each type and size of appurtenance required, including valve boxes,
<br />covers, and other associated items. (Except when included in lump sum bid items —
<br />eg; aerial crossing, directional bore, fire hydrant assembly, Connect to Existing)
<br />E. HDPE Horizontal Directional Bore: Measurement of HDPE horizontal directional
<br />bore shall be computed using linear feet, as measured above ground prior to
<br />pulling, and deducting the length of pipe cut off after the pull and shall include all
<br />material (including HDPE pipe), equipment, supplies, fuel, labor, sheeting and
<br />bracing, receiving and boring pits (if required), excavation, dewatering, backfilling,
<br />compaction, mechanical fittings, all adaptors, fusion welding of adaptors and pipe,
<br />restoration, furnishing and installation of the HDPE pipe. Payments shall be based
<br />on a linear foot price for the directional bore length as measured as specified above.
<br />F. Fire Hydrant Assembly: Measurement of fire hydrant assembly shall be for the
<br />actual number constructed in accordance with the Plans and Specifications, or as
<br />directed by the Engineer, at the unit price bid for the item "Fire Hydrant Assembly,"
<br />scheduled in the Form of Proposal. The unit price for "Fire Hydrant Assembly" shall
<br />include cutting bituminous paving, removal of paving courses and curb if required,
<br />excavations, furnishing and installation of 10' + (6") D.I.P. water main, dry -barrel
<br />traffic hydrant, concrete foundations for hydrant, fittings, one (1) 6" diameter gate
<br />valve, concrete thrust block (reaction backing) for fire hydrant, backfill, minor swale
<br />or shoulder right-of-way grading and sodding (per plans), blue reflective markers, all
<br />materials, equipment, labor and all else necessary therefore and incidental thereto.
<br />G. Water Service - (New): Measurement of water service lateral shall be for the actual
<br />number constructed in accordance with the plans and specifications, or as directed
<br />by the Engineer, at the unit price bid for each item "Water Service", and shall
<br />include furnishing and construction of piping and appurtenances to carry and
<br />distribute water from the water main to the edge of the Right -of -Way for future
<br />service to individual property owners. The work shall include, but shall not be
<br />limited to, cutting of existing pavement where required, jack and bore of existing
<br />pavement where required, excavation, installation (of pipe, meter boxes,
<br />connections and associated appurtenances), backfilling, testing, disinfection, and all
<br />restoration in kind. The services shall be of a type and size specified, and shall be
<br />constructed in accordance with these Plans and Specification, or as directed by the
<br />Engineer.