Laserfiche WebLink
SECTION 01311 <br />CONSTRUCTION SCHEDULES <br />PART 1 -- GENERAL <br />1.01 REQUIREMENTS INCLUDED <br />A. Promptly after award of the Contract, Contractor shall prepare and <br />submit to the Engineer estimated construction progress for the Work, <br />with sub -schedules of related activities which are essential to its <br />progress. <br />B. Coordinate the work and scheduling with and around other contractors <br />and individual trades performing work on the Project. <br />C. Submit revised progress schedules with each application for payment. <br />D. Progress Schedule shall become part of Contract Documents after <br />approval by Engineer. <br />1.02 RELATED REQUIREMENTS <br />A. In other parts of the Contract Documents: <br />1. General Conditions: <br />a. Articles 2 and 6 — Schedules, Reports, and Records <br />b. Sections 6.1 and 6.2 — Supervision by Contractor <br />C. Article 15 — Supervision of Work, Termination, and <br />Delay <br />B. Specified in other sections: <br />1. Section 01000: Summary of Work <br />2. Section 01201: Preconstruction Conference <br />3. Section 01340: Shop Drawings, Product Data, and Samples <br />1.03 FORM OF SCHEDULES <br />A. Prepare schedules in the form of a horizontal bar chart as follows: <br />1. Provide separate horizontal bar for each trade or operation <br />2. Horizontal time scale: Identify the first work day of each week. <br />3. Scale and spacing: To allow space for notations and future <br />revisions. <br />4. Minimum sheet size: 11" x 17" <br />01311 - 1 <br />