Laserfiche WebLink
B. Format of listings: The chronological order of the start of each item of <br />work. <br />C. Identification of listings: By major specification section numbers. <br />1.04 CONTENT OF SCHEDULES <br />A. Construction Progress Schedule shall: <br />1. Show the complete sequence of construction by activity. <br />2. Show the dates for the beginning and completion of each major <br />element of construction; specifically list: <br />a. Subcontractor work <br />b• Utility construction <br />C. Restoration <br />3. Show projected percentage of completion for each item, as of <br />the first day of each month. <br />LOS PROGRESS REVISIONS <br />A. Indicate progress of each activity to date of submission <br />B. Show changes occurring since previous submission of Schedule: <br />1. Major changes in scope. <br />2. Activities modified since previous submission. <br />3. Revised projections of progress and completion. <br />4. Other identifiable changes. <br />C. Provide a narrative report as needed to define: <br />1. Problem areas, anticipated delays, and the impact on the <br />schedule. <br />2. Corrective action recommended, and its effect. <br />3. The effect of changes on schedules of other prime contractors. <br />1.06 SUBMISSIONS <br />A. Submit initial schedules within ten (10) days after award of Contract; <br />Engineer will review schedules for information only. <br />B. Submit revised progress schedules with each application for payment. <br />01311 -2 <br />