Except for: (a) Claims for differing subsurface or physical conditionsgovemed <br />and (b) claims for time extensions governed by paragraphand other <br />by paragraph 12.03, all matters in question and other <br />matters between Owner and Contractor arising prior to the date final payment is due, relating to the <br />acceptability of the Work and the interpretation of the requirements of the contract documents <br />pertaining to the performance of the Work, will be referred initially to Engineer in writing within 15 <br />days after occurrence of the event giving rise to such Claim or within 15 days after the claimant first <br />recognizes the condition giving rise to the Claim, whichever is later, provided, however, the Owner <br />shall make all final determination of such matters. <br />SC 9.08-C Delete paragraph 9.08-C of the General Conditions in its entirety <br />SC 9.08-D Delete paragraph 9.08-D of the General Conditions in its entirety <br />SC 10.03 A.3 Delete subparagraph 10.03.A.3 of the General Conditions in its entirety <br />SC 10.05A Delete paragraph 10.05A of the General Conditions in its entirety and replace with the <br />following: <br />A. All Claims shall initially be referred to the Engineer for decision. <br />SC 10.05.8 Delete paragraph 10.05.B of the General Conditions in its entirety and replace with the <br />following: <br />Except for: (a) Claims for differing subsurface or physical conditions govemed by paragraph 4.03; <br />and (b) claims for time extensions govemed by paragraph 12.03, Claims by either party shall be <br />initiated within 15 days after occurrence of the event giving rise to such Claim or within 15 days after <br />the claimant first recognizes the condition giving rise to the Claim, whichever is later, by written <br />notice of the amount or extent of the Claim, dispute, or other matter with supporting data to the <br />Engineer and the other party by written notice stating the general nature of each Claim, dispute, or <br />other matter delivered by the claimant to Engineer and the other party to the Contract A Claim for an <br />adjustment in Contract Price shall be prepared in accordance with the provisions of paragraph <br />12.01.8. A Claim for an adjustment in Contract Time shall be prepared in accordance with the <br />provisions of paragraph 12.02.B. No daim by the Contractor for an equitable adjustment hereunder <br />shall be allowed if asserted after final payment under this Contract. <br />SC 10.05 C Delete paragraph 10.05C of the General Conditions in its entirety. <br />SC 10.05 D and E Delete paragraphs 10.05.0 and E of the General Conditions in their entirety <br />ARTICLE 11 - COST QF THE WORK; ALLOWANCES; UNIT PRICE WORK <br />SC -11.02A Delete paragraph 11.02.A of the General Conditions in its entirety and replace with the <br />following: <br />It is understood that CONTRACTOR has included in the Contract Price all allowances so named in <br />the Contract Documents and shall cause the Work so covered to be performed for such sums as <br />may be acceptable to OWNER. <br />Delete paragraphs 11.028 through D of the General Conditions in their entirety. <br />00800-11 <br />H1Projects107411Bidding Contract Specifications1Spec Template1200710080o1supplernentary Conditions.doc <br />