CLARIFICATIONS: <br />In the Project Pre -Bid Minute Meetings (Addendum No. 1), a Question was asked "Provide requirements <br />for scoreboard." Answer "(2) scoreboards will be included in the bid. The specifications for the <br />scoreboards will be issued in a pending addendum." The specifications for the 2 scoreboards are <br />attached hereto in Section 116625 Gymnasium Scoreboard. <br />In Addendum No. 2, Question No. 2 read "There does not appear to be a specification for the 3 flag poles. <br />Will one be made available? Answer No. 2 stated "No flag poles are to be included on the project. Their <br />removal will be noted and incorporated within the pending drawing addendum." Please see RC -L1 -01- <br />02 -LANDSCAPE PLAN.pdf <br />QUESTIONS AND ANSWERS: <br />QUESTION NO. 1 <br />Please provide Fixture specifications for Type X fixture (Exit Lights). None shown on sheet E1.00.00. <br />ANSWER NO. 1 <br />Gymnasium area: Provide LED thin profile, brushed aluminum, green letters, self-contained battery with self- <br />test/self-diagnostics, wire guard; EXITRONIX #G402/403 -WB -BA -G2 -WG**; in the remaining areas, provide LED <br />edge -lit exit light, recessed, with battery, green letters/mirror panel, white finish, self-test/self-diagnostics, <br />EXITRONIX 902/903-R-WB-GM-**-WH-G2; 277V for both types; contractor is to provide counts for double face, <br />single face, wall/ceiling/universal mount, directional arrows, appropriate wire guard selection, per the lighting <br />plans. <br />QUESTION NO. 2 <br />Is there a contractor doing the fountain? Is the scope for electrical contractor to provide power to vault only? <br />Who is providing Fountain lights? <br />ANSWER NO. 2 <br />Similar question was asked in IRC Bidding Questions Addendum #3, Question No. 13 in reference to the <br />fountain vault. Please refer to responses that addendum. In addition, the scope of Division 26 is to <br />provide disconnecting means and single point power connection to fountain equipment control panel <br />only. Fountain lights, fountain pump, control wiring, control panel would be by the fountain equipment <br />vendor/installer. <br />QUESTION NO. 3 <br />Please provide cut sheets for types P1 and P1E not on fixture schedule. Also, I found no counts for types and J1 <br />Fixtures. Have those fixtures been eliminated? <br />Page 2 of 20 <br />F:\Public Works\ENGINEERING DIVISION PROIECTS11135-S County Park Inlergeneratiional Rec Facility \Admim\ADDENDUMS\Addendum No. 4 I I-12-2014.doc <br />