JUSTIFICATION OF CHANGE ORDER NUMBER 2
<br />Water System Improvements Contract Part II
<br />R. 0. Equipment
<br />South County Water System
<br />Indian River County, Florida
<br />Section 2A, paragraph 2.A (3)d of the contract documents for contract part II
<br />states: ., .
<br />"The Contractor shall furnish, at his expense, the services of a factory trained
<br />serviceman to check and certify the installation of the equipment, instruct the
<br />Owners personnel, pl&ce the equipment in service and calibrate and adjust each iter,
<br />of equipment. Service shall be furnished for at least ninety (90), eight hour
<br />man -days at the job site, including a minimum of thirty (30) days during start up.
<br />Any additional services will be paid for at a per diem rate as specified by the
<br />Bidder in the appropriate space in the Bid".
<br />Water Services of America, Ing. bid a per diem rate of $530.00 per eight hour day
<br />.as stated in their original Bid. This Change Order represents costs incurred by
<br />Water Services of America, Inc. for technical services provided in addition to the
<br />90 days specified in Section 2A, paragraph 2,a (3)d'of the Contract Documents.
<br />The total amount invoiced by Water Services of America, Inc, is $18,583.13, which
<br />represents a total of 280.5 hours of additional tecnical service. (see attachments)
<br />After evaluation of the timesheets representing the 280.5 hours of service, it was
<br />determined that 75 hours of this total was service associated with corrective work
<br />and punch list items which are not covered by the specified per diem rate.
<br />Therefore, justification for change order #2 is based on additional technical servi
<br />provided by Water Services of America, Inc. for 205.5 hours or a total Contract
<br />increase of $13,614.38
<br />Sverdrup & Parcel and Associates, Inc.
<br />57
<br />NOV 16 1983
<br />July 26, 1983'
<br />' C
<br />�
<br />JUSTIFICATION OF CHANGE ORDER NUMBER 2
<br />Water System Improvements Contract Part II
<br />R. 0. Equipment
<br />South County Water System
<br />Indian River County, Florida
<br />Section 2A, paragraph 2.A (3)d of the contract documents for contract part II
<br />states: ., .
<br />"The Contractor shall furnish, at his expense, the services of a factory trained
<br />serviceman to check and certify the installation of the equipment, instruct the
<br />Owners personnel, pl&ce the equipment in service and calibrate and adjust each iter,
<br />of equipment. Service shall be furnished for at least ninety (90), eight hour
<br />man -days at the job site, including a minimum of thirty (30) days during start up.
<br />Any additional services will be paid for at a per diem rate as specified by the
<br />Bidder in the appropriate space in the Bid".
<br />Water Services of America, Ing. bid a per diem rate of $530.00 per eight hour day
<br />.as stated in their original Bid. This Change Order represents costs incurred by
<br />Water Services of America, Inc. for technical services provided in addition to the
<br />90 days specified in Section 2A, paragraph 2,a (3)d'of the Contract Documents.
<br />The total amount invoiced by Water Services of America, Inc, is $18,583.13, which
<br />represents a total of 280.5 hours of additional tecnical service. (see attachments)
<br />After evaluation of the timesheets representing the 280.5 hours of service, it was
<br />determined that 75 hours of this total was service associated with corrective work
<br />and punch list items which are not covered by the specified per diem rate.
<br />Therefore, justification for change order #2 is based on additional technical servi
<br />provided by Water Services of America, Inc. for 205.5 hours or a total Contract
<br />increase of $13,614.38
<br />Sverdrup & Parcel and Associates, Inc.
<br />57