Laserfiche WebLink
JUSTIFICATION OF CHANGE ORDER NUMBER 2 <br />Water System Improvements Contract Part II <br />R. 0. Equipment <br />South County Water System <br />Indian River County, Florida <br />Section 2A, paragraph 2.A (3)d of the contract documents for contract part II <br />states: ., . <br />"The Contractor shall furnish, at his expense, the services of a factory trained <br />serviceman to check and certify the installation of the equipment, instruct the <br />Owners personnel, pl&ce the equipment in service and calibrate and adjust each iter, <br />of equipment. Service shall be furnished for at least ninety (90), eight hour <br />man -days at the job site, including a minimum of thirty (30) days during start up. <br />Any additional services will be paid for at a per diem rate as specified by the <br />Bidder in the appropriate space in the Bid". <br />Water Services of America, Ing. bid a per diem rate of $530.00 per eight hour day <br />.as stated in their original Bid. This Change Order represents costs incurred by <br />Water Services of America, Inc. for technical services provided in addition to the <br />90 days specified in Section 2A, paragraph 2,a (3)d'of the Contract Documents. <br />The total amount invoiced by Water Services of America, Inc, is $18,583.13, which <br />represents a total of 280.5 hours of additional tecnical service. (see attachments) <br />After evaluation of the timesheets representing the 280.5 hours of service, it was <br />determined that 75 hours of this total was service associated with corrective work <br />and punch list items which are not covered by the specified per diem rate. <br />Therefore, justification for change order #2 is based on additional technical servi <br />provided by Water Services of America, Inc. for 205.5 hours or a total Contract <br />increase of $13,614.38 <br />Sverdrup & Parcel and Associates, Inc. <br />57 <br />NOV 16 1983 <br />July 26, 1983' <br />' C <br />� <br />JUSTIFICATION OF CHANGE ORDER NUMBER 2 <br />Water System Improvements Contract Part II <br />R. 0. Equipment <br />South County Water System <br />Indian River County, Florida <br />Section 2A, paragraph 2.A (3)d of the contract documents for contract part II <br />states: ., . <br />"The Contractor shall furnish, at his expense, the services of a factory trained <br />serviceman to check and certify the installation of the equipment, instruct the <br />Owners personnel, pl&ce the equipment in service and calibrate and adjust each iter, <br />of equipment. Service shall be furnished for at least ninety (90), eight hour <br />man -days at the job site, including a minimum of thirty (30) days during start up. <br />Any additional services will be paid for at a per diem rate as specified by the <br />Bidder in the appropriate space in the Bid". <br />Water Services of America, Ing. bid a per diem rate of $530.00 per eight hour day <br />.as stated in their original Bid. This Change Order represents costs incurred by <br />Water Services of America, Inc. for technical services provided in addition to the <br />90 days specified in Section 2A, paragraph 2,a (3)d'of the Contract Documents. <br />The total amount invoiced by Water Services of America, Inc, is $18,583.13, which <br />represents a total of 280.5 hours of additional tecnical service. (see attachments) <br />After evaluation of the timesheets representing the 280.5 hours of service, it was <br />determined that 75 hours of this total was service associated with corrective work <br />and punch list items which are not covered by the specified per diem rate. <br />Therefore, justification for change order #2 is based on additional technical servi <br />provided by Water Services of America, Inc. for 205.5 hours or a total Contract <br />increase of $13,614.38 <br />Sverdrup & Parcel and Associates, Inc. <br />57 <br />NOV 16 1983 <br />July 26, 1983' <br />