L. Change Order, Final Payment & Acceptance, Tracking <br />Station, Division 1 & 5 <br />Director Davis reviewed his memo, as follows: <br />TO: The Honorable Members of DATE: February 29, 1984 FILE <br />the Board of County Commissioners <br />THROUGH:Michael Wright, <br />County Administrator <br />SUBJECT: Request for Approval of Change <br />Orders, Final Payment, and,,,Fina�; <br />Acceptance - Project 8201 - <br />Tracking Station Park <br />Division I - Restroom and Site <br />Work-J.B. Construction Inc. <br />FROM:�-- <br />James W.`'Daviz, p.E.,: Division V - Paving and Drainage <br />Public Works Director Dickerson, Inc. <br />DESCRIPTION AND CONDITIONS <br />Dickerson_, Inc., and J.B. Walker Construction, Inc., have <br />completed the work as per contract requirements at the Tracking <br />Station Park. The work was -substantially complete on Feb. 7, 1984 <br />for both contracts. Dickerson's contract time of completion was <br />June 1, 1983. Due to delays caused by the other contractors <br />performing work at the park, a time extension of 119 days is <br />required to waive liquidated damages under the contract. A -change <br />order has been prepared to extend the contract date to Feb. 7, 1984 <br />and also to reconcile as -built quantities with design quantities. <br />The final cost to the County is $58,412.54 as compared to the <br />original contract cost of $58,489,.37. <br />J.B. Walker's contract time of completion was December 3, <br />1983. Due to delays caused by a late award of contract to the <br />Irrigation Contractor, a time extension of 66 calendar days is <br />required to waive liquidated damages under the contract. A change <br />order has been prepared to extend the contract date to Feb. 7,1984. <br />The final cost to the County for this Division -is $100,133.00 which <br />includes the previously approved $400 change order for electrical <br />work. <br />The Public Works Division and Parks Department have performed <br />final inspections and the attached descrepancy item letters were <br />forwarded. J.B. Walker Construction, Inc., has transmitted the <br />required release of lein affidavits and Final Payment form showing <br />10% being retained by the County for a maintenance bond. Dickerson <br />has not yet submitted a revised pay request form nor release of <br />lein affidavits. <br />ALTERNATIVES AND ANALYSIS <br />The County Public Works Division anticipates all work being <br />completed prior to March 7, 1984. Final payment approval, Final <br />Change Order, and Final Acceptance of the Work can be approved <br />subject to all work being completed by March 7, 1984, and the <br />County receiving the Final affidavits and Payment forms. <br />21 <br />MAR 7 1984 elox 5 PAGE 2- 101,01 <br />