inspection with OWNER and CONTRACTOR and will <br /> 14.05 Partial Utilization notify CONTRACTOR in writing of all particulars in <br /> which this inspection reveals that the Work is <br /> A. Use by OWNER at OWN ER's option of any incomplete or defective. CONTRACTOR shall <br /> substantially completed park of the Work which has immediately take such measures as are necessary to <br /> specifically been identified in the Contract Documents, complete such Work or remedy such deficiencies. <br /> or which OWNER, ENGINEER, and CONTRACTOR <br /> agree constitutes a separately functioning and usable 14.07 Final Payment <br /> part of the Work that can be used by OWNER for its <br /> intended purpose without significant interference with A. Application for Payment <br /> CONTRACTOR's performance of the remainder of <br /> the Work, may be accomplished prior to Substantial 1. After CONTRACTOR has, in the <br /> Completion of all the Work subject to the following opinion of ENGINEER, satisfactorily completed <br /> conditions. all corrections identified during the final <br /> inspection and has delivered, in accordance <br /> 1. OWNER at any time may request with the Contract Documents, all maintenance <br /> CONTRACTOR in writing to permit OWNER to and operating instructions, schedules, guaran- <br /> use any such part of the Work which OWNER tees, Bonds, certificates or other evidence of <br /> believes to be ready for its intended use and insurance certificates of inspection, marked-up <br /> substantially complete. If CONTRACTOR record documents (as provided in paragraph <br /> agrees that such part of the Work is 6.12), and other documents, CONTRACTOR <br /> substantially complete, CONTRACTOR will may make application for final payment follow- <br /> certify to OWNER and ENGINEER that such ing the procedure for progress payments. <br /> part of the Work is substantially complete and <br /> request ENGINEER to issue a certificate of 2. The final Application for Payment <br /> Substantial Completion for that part of the shall be accompanied (except as previously <br /> Work. CONTRACTOR at any time may notify delivered) by: (i) all documentation called for in <br /> OWNER and ENGINEER in writing that the Contract Documents, including but not <br /> CONTRACTOR considers any such part of the limited to the evidence of insurance required by <br /> Work ready for its intended use and substan- subparagraph 5.04.B.7; (ii) consent of the <br /> tially complete and request ENGINEER to issue surety, if any, to final payment; and (iii) <br /> a certificate of Substantial Completion for that complete and legally effective releases or <br /> part of the Work. Within a reasonable time waivers (satisfactory to OWNER) of all Lien <br /> after either such request, OWNER, rights arising out of or Liens filed in connection <br /> CONTRACTOR, and ENGINEER shall make with the Work. <br /> an inspection of that part of the Work to <br /> determine its status of completion. If 3. In lieu of the releases or waivers of <br /> ENGINEER does not consider that part of the Liens specified in paragraph 14.07.A.2 and as <br /> Work to be substantially complete, ENGINEER approved by OWNER, CONTRACTOR may <br /> will notify OWNER and CONTRACTOR in furnish receipts or releases in full and an <br /> writing giving the reasons therefor. If affidavit of CONTRACTOR that: (i)the releases <br /> ENGINEER considers that part of the Work to and receipts include all labor, services, <br /> be substantially complete, the provisions of material, and equipment for which a Lien could <br /> paragraph 14.04 will apply with respect to be filed; and (ii) all payrolls, material and <br /> certification of Substantial Completion of that equipment bills, and other indebtedness <br /> part of the Work and the division of connected with the Work for which OWNER or <br /> responsibility in respect thereof and access OWNER's property might in any way be <br /> thereto. responsible have been paid or otherwise satis- <br /> fied. If any Subcontractor or Supplier fails to <br /> 2. No occupancy or separate operation furnish such a release or receipt in full, CON- <br /> of part of the Work may occur prior to TRACTOR may furnish a Bond or other <br /> compliance with the requirements of paragraph collateral satisfactory to OWNER to indemnify <br /> 5.10 regarding property insurance. OWNER against any Lien. <br /> 14.06 Final Inspection B. Review of Application and Acceptance <br /> A. Upon written notice from CONTRACTOR that 1. If, on the basis of ENGINEER's <br /> the entire Work or an agreed portion thereof is observation of the Work during construction <br /> complete, ENGINEER will promptly make a final and final inspection, and ENGINEER's review <br /> 00704-General Conditions REV 04-07.doc <br /> 00700-40 <br /> FAPublic Works\ENGINEERING DIVISION PRGJECTS\1210-Sandridge Driving Range Tee Renovation\Admimlbid documents100700_General Conditions REV 04-07.doe <br /> SmeadSoft Reprint Date:Monday,January 11,2016-09:22:11-OfficialDocuments:9069,Attachment Id 1,Page 107 <br />