A. The OWNER shall make progress payments to the CONTRACTOR on the basis of <br />the approved partial payment request as recommended by ENGINEER in <br />accordance with the provisions of the Local Government Prompt Payment Act, <br />Florida Statutes section 218.70 et. seq. The OWNER shall retain ten percent <br />(10%) of the payment amounts due to the CONTRACTOR until fifty percent <br />(50%) completion of the work. After fifty percent (50%) completion of the work is <br />attained as certified to OWNER by ENGINEER in writing, OWNER shall retain <br />five percent (5%) of the payment amount due to CONTRACTOR until final <br />completion and acceptance of all work to be performed by CONTRACTOR under <br />the Contract Documents. Pursuant to Florida Statutessection 218.735(8)(b), fifty <br />percent (50%) completion means the point at which the County as OWNER has <br />expended fifty percent (50%) of the total cost of the construction services work <br />purchased under the Contract Documents, togetlerwith all costs associated with <br />existing change orders and other additions or mcationss to the construction <br />services work provided under the Contract Documents <br />6.03 Pay Requests. <br />A. Each request for a progress payment shall be submitted on the application for <br />payment form supplied by OWNER and th.application for y,.ment shall contain <br />the CONTRACTOR'S certification. All progress pay encs ill be on the basis of <br />progress of the work measured by the schedule of valu,ss established, or in the <br />case of unit price work based on he number of units completed. After fifty <br />percent (50%) completion, and pursuant to Florida Statutes section <br />218.735(8)(d), the CONTACTOR. may submit a pay request to the County as <br />OWNER for up to one half 12) ofhe retainage held by the County as OWNER, <br />and the County as OWNER s gall promptly make payment to the CONTRACTOR <br />unless such amounts are the subjectoa good faith dispute; the subject of a <br />claim pursuant toi=�l'orida Statutes section 255.05(2005); or otherwise the subject <br />of talaim or dem' by the .County as OWNER or the CONTRACTOR. The <br />CONT CJOR acknowledges that where such retainage is attributable' to the <br />labor, services;- or: matels su <br />riapplied by one or more subcontractors or suppliers, <br />the Contactor s all timely remit payment of such retainage to those <br />subcontractors -'and' ;suppliers. Pursuant to Florida Statutes section <br />218.735(8)(02005), CONTRACTOR further acknowledges and agrees that: 1) <br />theeBounty as, .OWNER shall receive immediate written notice of all decisions <br />by;CONRACTOR to withhold retainage on any subcontractor at greater <br />than five &. pereent (5%) after fifty percent (50%) ) completion; and 2) <br />CONTRACTOR will not seek release from the County as OWNER of the <br />withheld retainage until the final pay request. <br />6.04 Paragraphs 6.02 and 6.03 do not apply to construction services work purchased by the <br />County as OWNER which are paid for, in whole or in part, with federal funds and are subject to <br />federal grantor laws and regulations or requirements that are contrary to any provision of the <br />Local Government Prompt Payment Act. In such event, payment and retainage provisions shall <br />be governed by the applicable grant requirements and guidelines. <br />6.05 Acceptance of Final Payment as Release. <br />A. The acceptance by the CONTRACTOR of final payment shall be and shall operate <br />as a release to the OWNER from all claims and all liability to the CONTRACTOR <br />other than claims in stated amounts as may be specifically excepted by the <br />00520 - Agreement (Public Works) SAMPLE <br />00520 - 4 <br />F\Public Works\ENGINEERING DIVISION PROJECTS\1304-CR 512 Resurf (SCOP)_125th Ave to I-951Admim\agenda items100520 - Agreement (Public Works) SAMPLE.doc <br />38 <br />