of CONTRACTOR's intention to cover the same and <br /> ENGINEER has not acted with reasonable prompt- any of thefR-. <br /> ness in response to such notice. <br /> 13 04 Uncovering Work 13 06 Correction or Removal of Defective Work <br /> A. CONTRACTOR shall correct all defective <br /> A. If any Work is covered contrary to the written Work, whether or not fabricated, installed, or <br /> request of ENGINEER, it must, if requested by ENGI- completed, or, if the Work has been rejected by ENGI- <br /> NEER, be uncovered for ENGINEER's observation NEER, remove it from the Project and replace it with <br /> and replaced at CONTRACTOR's expense. Work that is not defective. CONTRACTOR shall pay <br /> all Claims, costs, losses, and damages (including but <br /> B. If ENGINEER considers it necessary or not limited to all fees and charges of engineers, <br /> advisable that covered Work be observed by ENGI- architects, attorneys, and other professionals and all <br /> NEER or inspected or tested by others, CONTRAC- court or arbitration or other dispute resolution costs) <br /> TOR, at ENGINEER's request, shall uncover, expose, arising out of or relating to such correction or removal <br /> or otherwise make available for observation, inspec- (including but not limited to all costs of repair or <br /> tion, or testing as ENGINEER may require, that replacement of work of others). <br /> portion of the Work in question, furnishing all neces- <br /> sary labor, material, and equipment. If it is found that 13 07 Correction Period <br /> such Work is defective, CONTRACTOR shall pay all <br /> Claims, costs, losses, and damages (including but not A. <br /> limited to all fees and charges of engineers, architects, Gempletion OF GUGh longell: peried of time as may be <br /> attorneys, and other professionals and all court or preSGrobed by Laws eF Regulations 9F by the terms 9 <br /> arbitration or other dispute resolution costs) arising out any appliGable 6peGial quaFaRtee required by thee <br /> of or relating to such uncovering, exposure, observa- <br /> tion, inspection, and testing, and of satisfactory GORtrar-3t I)GGlUments, aRY Work is found to he <br /> replacement or reconstruction (including but not defeGtive, 9F wf the Fepair of any damages to the - <br /> limited to all costs of repair or replacement of work of 9F areas Made available for GONTRACTOR'F; --lu.-by <br /> others); and OWNER shall be entitled to an n,n11NIFEp or permitter! by Laws and Reg ulatienn as <br /> appropriate decrease in the Contract Price If the Genternpiated OR paFagFaph 6.11.A is; feund to he <br /> parties are unable to agree as to the amount thereof, <br /> OWNER may make a Claim therefor as provided in <br /> paragraph 10.05. If, however, such Work is not found <br /> to be defective, CONTRACTOR shall be allowed an <br /> increase in the Contract Price or an extension of the \Aferk has been reie^ted by OWNER, remove it from <br /> Contract Times (or Milestones), or both, directly <br /> attributable to such uncovering, exposure, <br /> observation, inspection, testing, replacement, and to the <br /> ' <br /> reconstruction. If the parties are unable to agree as to iaeof ethers er ether I-anii er ^reas res Mine <br /> rlr them <br /> the amount or extent thereof, CONTRACTOR may frnrn If CONTRACTOR does not promptly comply <br /> make a Claim therefor as provided in paragraph with the terms of such instructions, or in an <br /> 10.05. emergency where delay would cause serious risk of <br /> loss or damage, OWNER may have the defective <br /> 13.05 OWNER May Stop the Work Work corrected or repaired or may have the rejected <br /> Work removed and replaced, and all Claims, costs, <br /> losses, and damages (including but not limited to all <br /> fails to sdPPly—sa#c>FenslFiRedRers ;a fees and charges of engineers, architects, attorneys, <br /> and other professionals and all court or arbitration or <br /> other dispute resolution costs) arising out of or relating <br /> to such correction or repair or such removal and <br /> TRACTOR to stGp the WeFk, or any portion thereGf, replacement (including but not limited to all costs of <br /> repair or replacement of work of others)will be paid by <br /> however, thils Fight ef OWNER te stop the Wark 6hall CONTRACTOR. <br /> not give rise to any duty GR the part of OWNER to <br /> B <br /> befeFe Substantial Completion of all the Werk, <br /> 00700-General Conditions REV 5-10-13.doc <br /> 00700-37 <br /> F\Public WorkMENGINEERING DIVISION PROJECTS\0845B-Old Dixie Hwy Sidewalk(38th Ln-45th St)V+dmim\bid documentsWlaster Contract Documents\00700-General Conditions <br /> REV 5-10-13.doc <br />