schedule. The County may also grant an extension of Contract Time when a critical path item of work is <br />delayed by factors not reasonably anticipated or foreseeable at the time of bid or if failure of the County to <br />fulfill an obligation under the contract results in delays to the schedule critical path The County may consider <br />the delays in delivery of materials or equipment that affect progress on a critical item of work as the basis for <br />granting a time extension if such delays are beyond the control of the Contractor. Requests for time <br />extensions due to delay in the delivery of custom manufactured equipment or fixtures will not be considered <br />unless the contractor furnishes documentation that the order was placed in a timely manner and the lack of <br />such equipment cased a delay in progress on a critical item. <br />Extensions of Contract Time will not be granted for delays due to the fault or negligence of the <br />Contractor <br />No allowance for inclement weather should be made in establishing the Contract Time. The County <br />may grant time extensions on a day for day basis for delays caused only by inclement weather conditions that <br />prevent the contractor from productively performing critical path items where (i) the contractor is unable to <br />work at least 50% of the day on a pre -determined critical path item due to the weather; or (ii) the contractor <br />must make major repairs to work damaged by weather provided that the damage is not due to the contractor's <br />failure to perform and that the contractor is unable to work at least 50% of the day on pre -determined critical <br />path items. <br />24 LIQUIDATED DAMAGES <br />Applicable liquidated damages will be assessed in the following amount: $758.00 per day <br />25 CONTRACT CLAIMS BY CONTRACTOR <br />Should the contractor intend to file a claim for additional monetary compensation, time or other <br />adjustments to the contract and the County disputes the contractor's entitlement to the claim or the impact of <br />the claim, Contractor must provide written notification to the County of contractor's intent to file a claim. This <br />notice must be given before the contractor begins any work on which the claim is based. Failure of the <br />contractor to notify the County before beginning work on any disputed items waives the contractor's right to <br />claim The contractor's notice of intent to file a claim should contain. <br />(1) A statement as to what changed, including a description of the nature and extent of the <br />change. <br />(2) An indication of who directed or what caused the change. <br />(3) A description of how the change has or will impact the contractor, including reference to any <br />impacted critical activities on the contractor's latest accepted schedule update <br />(4) A statement of damages, or an estimate of damages if available, detailing the amount of <br />compensation, time and/or other adjustment to the contract that is being requested. <br />26 DRUG-FREE WORKPLACE CERTIFICATION <br />In accordance with Florida Statute 287 087, the bidder shall certify that it has and will maintain a drug-free <br />workplace The bidder shall complete and submit with its bid proposal the attached certification. Failure to <br />include an executed certification may cause the bid proposal to be considered non-responsive. <br />27 SUSPENSION AND DEBARMENT <br />The bidder shall complete and submit with its bid proposal the certification regarding debarment form included <br />in this package, or an explanation as provided herein The inability to provide the certification will not <br />necessarily result in denial of participation in the project. The bidder shall submit an explanation of why it <br />cannot provide the requested certification, which will be considered in evaluation of the bidder's bid package. <br />However, failure by a bidder to furnish a certification or an explanation shall disqualify such bidder from this <br />23 <br />