My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
3/3/1987
CBCC
>
Meetings
>
1980's
>
1987
>
3/3/1987
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
7/23/2015 11:59:17 AM
Creation date
6/12/2015 1:45:40 PM
Metadata
Fields
Template:
Meetings
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
68
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
G. Gravity Sewer Proj 11th St. &_7th Ct. (Change Orders) <br />The Board ,reviewed memo from Engineer Boone: <br />TO: BOARD OF COUNTY COMMISSIONERS DATE: FEBRUARY 17, 1987 <br />VIA: CHARLES P. BALCZUN <br />COUNTY ADMINISTRATOR <br />VIA: TERRANCE G. PINTO <PI <br />DIRECTOR OF UTILITY SERVICES <br />60 <br />FROM: JEFFREY A. BOONE <br />ts"MAN <br />ENGINEERING OPERAAGER <br />DIVISION OF UTILITY SERVICES <br />SUBJECT: INDIAN RIVER COUNTY UTILITIES PROJECT NO. <br />GRAVITY SEWER - 11TH STREET & 7TH COURT <br />CONSTRUCTION CHANGE ORDER NO. 1 <br />WORK AUTHORIZATION CHANGE ORDER NO. 1 <br />CONSTRUCTION CHANGE ORDER NO.2 <br />BACKGROUND <br />US86-17-CS <br />0 <br />On January 20, 1987, the Board of County -Commissioners authorized the <br />construction of a gravity wastewater collection system on 7th Court from <br />12th Street to 11th Street, continuing east on 11th Street from 7th <br />Court to 6th Avenue, and continuing south on 6th Avenue from 11th <br />Street, and connecting to an existing manhole. <br />After awarding the subject contract, it was confirmed that the Public <br />Works Division was prepared to pave 7th Court and 11th Street, as well <br />as 7th Avenue under the Petition Paving Program. With the paving of 7th <br />Avenue pending, the Division of Utility Services has had cost estimates <br />for construction prepared by Masteller & Moler Associates, Inc. to <br />expand the subject contract to include the construction of the gravity <br />wastewater collection line on 7th Avenue from 12th Street to lith <br />Street. <br />ANALYSIS <br />Attached for your review and approval is Construction Change Order No. <br />1: to add two (2) additional 6 inch diameter service laterals to the <br />previously approved construction. The additional service laterals <br />will serve adjacent commercial areas which currently have on-site <br />wastewater treatment facilities. Also attached for your review and <br />approval are Work Authorization Change Order No. 1 as well as <br />Construction Change Order No. 2 for additional engineering fees and <br />construction costs associated with expanding the subject contract to <br />include the construction of a gravity wastewater collection line on <br />7th Avenue from 12th Street to 11th Street. <br />Outlined below are the associated costs for the above-mentioned change <br />orders: <br />Description <br />Additional Total Additional <br />Engineering Engineering Construction <br />Costs Costs Costs <br />Total <br />Construction <br />Costs <br />Total <br />Project <br />Costs <br />Original Project Costs <br />Original <br />Project <br />Costs <br />$5400.00 <br />$60573.00 <br />$65973.00 <br />MAR 3 1987 11 BOOK 67 u,'-; X66 <br />
The URL can be used to link to this page
Your browser does not support the video tag.