SECTION 01014 <br />SPECIAL WORK SEQUENCES <br />PART 1 — GENERAL <br />1.01 SCOPE OF WORK <br />A. The purpose of this section is to summarize construction scheduling, labor, material, <br />equipment, and facility operation constraints and requirements which the Contractor shall <br />take into consideration when planning and scheduling work under this Contract. Work <br />will be performed at various locations for the North WTP Raw Water Transmission <br />System. <br />B. This Work shall be performed in such a manner as to minimize the disruption to the <br />operation and staff of the existing water treatment plant. Modifications that affect or may <br />affect the operation of the treatment facilities shall not be made without first obtaining <br />written permission from the OWNER. Disruptions include, but are not limited to: <br />1. Removing a process unit from service or impeding the operation of a process <br />unit. <br />2. Removing from service, restricting, or impeding the function of any utility <br />(water, electricity, compressed air, drains, sanitary sewer, storm drain, telephone, <br />instrumentation) serving any portion of a process unit, Operations Building, <br />maintenance room and electrical control room. <br />3. Removing from service, restricting, or impeding the function of any treatment <br />chemical storage, metering, conveyance, or application system. <br />4. Delaying or denying access to any plant structure or area needed by the IRC <br />operations personnel to complete their work assignments. <br />C. Extra precautions are necessary to ensure that no damage occurs to these facilities <br />including piping, utilities, roads, interiors of structures, and structures in general that are <br />to remain in operation and are not to be modified or replaced. Any temporary facilities, <br />materials, equipment, and labor required to ensure that no damage occurs shall be <br />provided by the Contractor as part of the Work and at no additional cost to the OWNER. <br />D. All interruptions, outages, interferences, or temporary shutdowns of plant facilities and <br />operations shall be identified and outlined before work is to be done. Requested times <br />and dates for these interruptions, outages, interferences, or temporary shutdowns shall be <br />scheduled on the construction progress schedule under Section 01311. A schedule of all <br />planned interruptions, outages, interferences, or temporary shutdowns of the plant <br />facilities and operations shall be submitted every month in accordance with Section <br />01311. This schedule shall include a minimum 2 -month planning horizon. <br />1.02 GENERAL REQUIREMENTS <br />A. The water treatment plant must provide continuous treatment capacity during the <br />construction period and meet its permit requirements under all operating conditions. <br />B. In general, no work which affects or could affect plant operations or plant performance <br />shall be performed without a specific detailed plan by the Contractor approved in <br />advance by the Engineer and the Owner. All requests for plant system diversions, <br />1 1 M <br />