My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2013-000 (2)
CBCC
>
Official Documents
>
2010's
>
2013
>
2013-000 (2)
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
4/27/2018 12:54:31 PM
Creation date
3/23/2016 9:12:18 AM
Metadata
Fields
Template:
Official Documents
Official Document Type
Bid
Approved Date
08/20/2013
Control Number
2013-000
Subject
Fertilizer and Landscape Management
Area
Old Dixie Highway Sidewalk 38th Lane to 45th Street
Alternate Name
Sidewalk Improvements
Supplemental fields
FilePath
H:\Indian River\Network Files\SL00000I\S0005EA.tif
Meeting Body
Board of County Commissioners
Meeting Type
BCC Regular Meeting
SmeadsoftID
14586
Document Relationships
2013-014
(Agenda)
Path:
\Ordinances\2010's\2013
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
178
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
GC 31 INSPECTION. <br /> Engineer: The Owner may provide Engineering personnel for the observation of the work. The <br /> Owner, Engineer and their representatives shall at all times have access to the work whenever it is in <br /> preparation or progress, and the Contractor shall provide proper facilities for such access and for inspection. <br /> If the specifications, the Engineer's instructions, applicable laws, ordinances, or any public authority require <br /> any work to be specially tested or approved, the Contractor shall give the Engineer timely notice of its <br /> readiness for observation and, if the observation is by another authority than the Engineer,of the date fixed for <br /> such observation. If any work should be covered up prior to any quality inspection or test by Owner or <br /> Engineer, it must, if required by the Engineer, be uncovered for inspection and properly restored at the <br /> Contractor's expense. <br /> GC 32 TESTING <br /> Unless otherwise provided in the Contract, drawings or specifications, shop testing of material or work <br /> shall be performed by the Contractor at its expense and in accordance with the technical specifications. <br /> Should tests in addition to those required by the specifications be desired by Owner, Contractor will be advised <br /> in reasonable time to permit such additional testing at Owner's expense, unless additional tests are required <br /> due to Contractor's work or materials having failed any initial test. Contractor shall furnish samples as <br /> requested and shall provide reasonable assistance and cooperation necessary to permit tests to be performed <br /> on materials or work in place, including reasonable stoppage of work during testing. <br /> GC 33 SUBSTITUTION. <br /> The naming of a specified product of specific manufacturers for equipment or materials under the <br /> various items of specifications or as shown on the plans shall be interpreted as establishing a minimum <br /> standard of quality and performance. It shall not be construed as eliminating the selection of other than the <br /> named equipment or materials equal to those specified, unless the materials are specifically designated as not <br /> permitting substitution. <br /> Prior to proposing any substitute item, Contractor shall satisfy itself that the item proposed is equal or <br /> better to that specified,that such item will fit into the space allocated, that such item affords comparable ease <br /> of operation , maintenance and service, that the appearance, longevity and suitability for the climate are <br /> comparable, that by reason of costs savings, reduced construction time or similar demonstrable benefit, the <br /> substitution of such item will be in Owner's interest and will in no way detrimentally impact the project <br /> schedule. The burden of proof that such an item offered is equal in all respects to that specified shall be the <br /> Contractor's. Contractor shall submit drawings, samples, data and additional information as may be required <br /> by Owner. All requests for substitutions,with supporting information, shall be submitted by and at the expense <br /> of Contractor. At least 35 days shall be allowed for Owner's review. <br /> The Owner or its Engineer shall make the determination as to the acceptability of any substitution. <br /> Approval of a substitution shall not relieve Contractor from the responsibility for compliance with all <br /> requirements of the Contractor. Contractor shall coordinate the change with all trades and bear the expense <br /> for any changes in other parts of the work caused by any substitution. <br /> Contractor may make only two requests for substitution in the same category and Contractor shall be <br /> invoiced the expenses incurred by Owner for its design professionals in reviewing additional substitution <br /> requests, unless otherwise approved by Owner. <br /> GC 34 CORRECTION OF DEFECTIVE MATERIALS OR WORKMANSHIP <br /> If any material, equipment or workmanship is determined by Owner, either during performance of the <br /> work, during final quality inspection or during the warranty period,to be defective or non in compliance with the <br /> specifications and the Contract, Owner shall notify Contractor in writing that such material,equipment or work <br /> is rejected and the Owner reserve the right to withhold payment on any such item. Contractor shall, at its own <br /> expense, immediately remove and replace or correct such defective material, equipment or work by making <br /> the same strictly comply with all requirements of the drawings, specifications and contract. If Owner or <br /> Engineer deems it inexpedient to correct work that has been damaged or that was not performed in <br /> accordance with the drawings, specifications and contract,an equitable deduction from the contract price shall <br /> 36 <br />
The URL can be used to link to this page
Your browser does not support the video tag.