SECTION 01310 <br /> CONSTRUCTION SCHEDULES <br /> 1.1 GENERAL REQUIREMENTS <br /> A. No partial payments shall be approved by the ENGINEER until there is an <br /> approved construction progress schedule on hand. <br /> B. Designate an authorized representative who shall be responsible for <br /> development and maintenance of the schedule and of all progress and <br /> payment reports. This representative shall have direct project control and <br /> complete authority to act on behalf of the CONTRACTOR in fulfilling the <br /> commitments of the CONTRACTOR's schedules. <br /> 1.2 REVISIONS TO THE CONSTRUCTION SCHEDULES <br /> When the ENGINEER requires the CONTRACTOR to submit revised (updated) <br /> progress schedules on a monthly basis the CONTRACTOR shall: <br /> A. Indicate the progress of each activity to the date of submission. <br /> B. Show changes occurring since the previous submission listing- <br /> 1. <br /> isting:1. Major changes in scope. <br /> 2. Activities modified since the previous submission. <br /> 3. Revised projections of progress and completion. <br /> 4. Other identifiable changes. <br /> C. Provide a narrative report as needed to define: <br /> 1. Problem areas, anticipated delays, and the impact on the schedule. <br /> 2. Corrective action recommended and its effect. <br /> 3. The effect of changes on schedules of other prime contractors. <br /> 1.3 SUBMISSION OF THE CONSTRUCTION SCHEDULES <br /> On or before the tenth day after the effective date of the Agreement, submit the <br /> initial schedules to the ENGINEER. The ENGINEER will review the schedules <br /> and return a review copy to the CONTRACTOR within 21 days after receipt. If <br /> required by the ENGINEER, resubmit revised schedules on or before the <br /> seventh day after receipt of the review copy. If required by the ENGINEER, <br /> submit revised monthly progress schedules with that month's application for <br /> payment. <br /> 01310-1 01310 Construction Schedule <br /> FAPublic Works\ENGINEERING DIVISION PROJECTS\0845B-Old Dixie Hwy Sidewalk(38th Ln-45th St)\Admim\bid <br /> documents\Master Contract Documents\01310-Construction Schedule.doc <br />