SECTION 00942 - Change Order Form No. 3 <br /> DATE OF ISSUANCE: November 19, 2013 EFFECTIVE DATE: November 19, 2013 <br /> ti... <br /> OWNER: Indian River County <br /> CONTRACTOR: Timothy Rose Contracting Inc <br /> Project:Old Dixie Highway Sidewalk Improvements from 8th Street to 20th Street <br /> OWNER's Project No. 1102 Bid No. 2012052 FM No.425710-1-58-01 <br /> ENGINEER Indian River County Engineering Division <br /> You are directed to make the following changes in the Contract Documents: Proceed with the repair of a 15" <br /> diameter reinforced concrete pipe at the southeast corner of 16th Street and Old Dixie Highway. <br /> Reason for Change Order: During the construction of a sidewalk ramp as part of the construction of the Old Dixie <br /> Highway Sidewalk Project, a pipe failure of a 15" Reinforced concrete pipe was discovered. The pipe failure must be <br /> repaired or further deterioration of the roadway will occur. This change order reflects the work necessary to perform <br /> the pipe repair. <br /> Time extensions: <br /> 60 days for additional work <br /> Work Change Directive No 2-32 days for rain delays. <br /> Total time extension is 92 days <br /> Attachments: Description of Itemized Changes <br /> Revised plan, Sheet 18 <br /> Proposal from Timothy Rose Contracting, Inc. dated October 17,2013 <br /> Work Change Directive No.2 (Rain delays) <br /> CHANGE IN CONTRACT CHANGE IN CONTRACT <br /> PRICE: TIMES <br /> Description Amount Description Time <br /> Original Contract Price $325,518.37 Original Contract Time: (days and dates) <br /> Substantial Completion: 120 days/6-12-13 <br /> Final Completion.- 150 davs/7-13-13 <br /> Net Increase from previous $41,283.57 Net change from previous <br /> Change Order No.s 1 &2 Change Order No.s 1 &2 (days) <br /> Substantial Completion: 90 <br /> Final Completion: 90 <br /> Contract Price prior to this $366,801.94 Contract Time prior to this <br /> Change Order: Change Order: (days and dates) <br /> Substantial Completion: 210 days/9-12-13 <br /> Final Completion: 240 days/ 10-12-13 <br /> Net increase of this Change $55,520.00 Net increase this Change Order <br /> Order No. 3: No. 3: (days) <br /> Substantial Completion: 92 days <br /> Final Completion: 92 days <br /> Contract Price with all $422,321.94 Contract Time with all approved <br /> approved Change Orders: Change Orders: (days and dates) <br /> Substantial Completion: 302 days/ 12-16-13 <br /> Final Completion: 1 332 days/ 1-18-14 <br /> ACCEPT RECOMMENDED: APPROVED.- <br /> By ..� By: <br /> CONTRACTOR (Signature) ENGINEER (Signature) OWNER (Signature) <br /> Date: `/ Date: //- /Z i3 Date: <br /> F\Public Works\ENGMERING DIVISION PROJECTSU 102-Old Dixie Hwy Swk 8th St to SR 60-LAP\Admim\Change Orders\Change Order No.3,PIPE FAILURE_doc <br /> 45 <br />