1. where the Work involved is covered <br />by unit prices contained in the Contract <br />Documents, by application of such unit prices to <br />the quantities of the items involved (subject to <br />the provisions of paragraph 11.03 ); or <br />2. where the Work involved is not cov- <br />ered by unit prices contained in the Contract <br />Documents, by a mutually agreed lump sum <br />(which may include an allowance for overhead <br />and profit not necessarily in accordance with <br />paragraph 12.01.C.2); or <br />3. where the Work involved is not cov- <br />ered by unit prices contained in the Contract <br />Documents and agreement to a lump sum is <br />not reached under paragraph 12.01.6.2, on the <br />basis of the Cost of the Work (determined as <br />provided in paragraph 11.01) plus a <br />CONTRACTOR's fee for overhead and profit <br />(determined as provided in paragraph 12.01.C). <br />C. CONTRACTOR's Fee: The <br />CONTRACTOR's fee for overhead and profit shall be <br />determined as follows: <br />1. a mutually acceptable fixed fee; or <br />2. if a fixed fee is not agreed upon, then <br />a fee based on the following percentages of the <br />various portions of the Cost of the Work: <br />a. for costs incurred under para- <br />graphs 11.01.A.1 and 11.01.A.2, the <br />CONTRACTOR's fee shall be 15 percent; <br />b. for costs incurred under paragraph <br />11.01.A.3, the CONTRACTOR's fee shall <br />be five percent; <br />c. where one or more tiers of subcon- <br />tracts are on the basis of Cost of the Work <br />plus a fee and no fixed fee is agreed upon, <br />the intent of paragraph 12.01.C.2.a is that <br />the Subcontractor who actually performs <br />the Work, at whatever tier, will be paid a fee <br />of 15 percent of the costs incurred by such <br />Subcontractor under paragraphs 11.01.A.1 <br />and 11.01.A.2 and that any higher tier <br />Subcontractor and CONTRACTOR will <br />each be paid a fee of five percent of the <br />amount paid to the next lower tier Subcon- <br />tractor, <br />d. no fee shall be payable on the <br />basis of costs itemized under paragraphs <br />11.01.A.4, 11.01.A5, and 11.01.6; <br />00700-34 <br />F:1Public Works\ENGINEERING DIVISION PROJECTS\1314-107th Ave Milling_90th St to 94th St'Admin\bid documents\Master Contract Documents\00700 - General Con•itions REV 5-10- <br />13.doc <br />e. the amount of credit t <br />by CONTRACTOR to OWN <br />change which results in a net <br />cost will be the amount of th <br />decrease in cost plus a <br />CONTRACTOR's fee by an a <br />to five percent of such net decr <br />f. when both additions an <br />involved in any one change, th <br />in CONTRACTOR's fee shall <br />on the basis of the net <br />accordance with paragraphs <br />through 12.01.C.2.e, inclusive. <br />12.02 Change of Contract Times <br />be allowed <br />R for any <br />decrease in <br />actual net <br />eduction in <br />ount equal <br />ase; and <br />credits are <br />adjustment <br />e computed <br />change in <br />12.01.C.2.a <br />A. The Contract Times (or Mileston: s) may only <br />be changed by a Change Order or b a Written <br />Amendment. Any Claim for an adjus ent in the <br />Contract Times (or Milestones) shall b based on <br />written notice submitted by the party maki g the claim <br />to the ENGINEER and the other party to he Contract <br />in accordance with the provisions of parag aph 10.05. <br />B. Any adjustment of the Contrac Times (or <br />Milestones) covered by a Change Ord =r or of any <br />Claim for an adjustment in the Contrac Times (or <br />Milestones) will be determined in accorda ce with the <br />provisions of this Article 12. <br />12.03 Delays Beyond CONTRACTOR' <br />A. Where CONTRACTOR is prey <br />completing any part of the Work within t <br />Times (or Milestones) due to delay beyon <br />of CONTRACTOR, the Contract <br />Milestones) will be extended in an amount <br />time lost due to such delay if a Claim is m <br />as provided in paragraph 12.02.A. Delays <br />control of CONTRACTOR shall include, <br />limited to, acts or neglect by OWNER, act <br />of utility owners or other contractors perfo <br />work as contemplated by Article 7, fi <br />epidemics, abnormal weather conditions, <br />God. <br />Control <br />nted from <br />e Contract <br />the control <br />imes (or <br />qual to the <br />de therefor <br />beyond the <br />but not be <br />or neglect <br />ing other <br />es, floods, <br />or acts of <br />12.04 Delays Within CONTRACTOR's l ontrol <br />A. The Contract Times (or Milestone-) will not be <br />extended due to delays within the control of <br />CONTRACTOR. Delays attributable to an• within the <br />control of a Subcontractor or Supplie shall be <br />deemed to be delays within the control of ONTRAC- <br />TOR. <br />12.05 Delays Beyond OWNE''s and <br />CONTRACTOR's Control <br />00700 - General Condition REV 5-10-13.doc <br />