establish the standards by which such portion of the
<br />Work will be judged.
<br />39. Shop Drawings—All drawings, diagrams,
<br />illustrations, schedules, and other data or information
<br />which are specifically prepared or assembled by or for
<br />CONTRACTOR and submitted by CONTRACTOR to
<br />illustrate some portion of the Work.
<br />40. Site—Lands or areas indicated in the
<br />Contract Documents as being furnished by OWNER
<br />upon which the Work is to be performed, including
<br />rights-of-way and easements for access thereto, and
<br />such other lands furnished by OWNER which are
<br />designated for the use of CONTRACTOR.
<br />41. Specifications—That part of the Contract
<br />Documents consisting of written technical descriptions
<br />of materials, equipment, systems, standards, and
<br />workmanship as applied to the Work and certain
<br />administrative details applicable thereto.
<br />42. Subcontractor—An individual or entity
<br />having a direct contract with CONTRACTOR or with
<br />any other Subcontractor for the performance of a part
<br />of the Work at the Site.
<br />43. Substantial Completion—The time at
<br />which the Work (or a specified part thereof) has
<br />progressed to the point where, in the opinion of
<br />ENGINEER, the Work (or a specified part thereof) is
<br />sufficiently complete, in accordance with the Contract
<br />Documents, so that the Work (or a specified part
<br />thereof) can be utilized for the purposes for which it is
<br />intended. The terms "substantially complete" and
<br />"substantially completed" as applied to all or part of the
<br />Work refer to Substantial Completion thereof.
<br />44. Supplementary Conditions—That part of
<br />the Contract Documents which amends or
<br />supplements these General Conditions.
<br />45. Supplier—A manufacturer, fabricator,
<br />supplier, distributor, materialman, or vendor having a
<br />direct contract with CONTRACTOR or with any
<br />Subcontractor to fumish materials or equipment to be
<br />incorporated in the Work by CONTRACTOR or any
<br />Subcontractor.
<br />46. Underground Facilities—All underground
<br />pipelines, conduits, ducts, cables, wires, manholes,
<br />vaults, tanks, tunnels, or other such facilities or
<br />attachments, and any encasements containing such
<br />facilities, including those that convey electricity, gases,
<br />steam, liquid petroleum products, telephone or other
<br />communications, cable television, water, wastewater,
<br />storm water, other liquids or chemicals, or traffic or
<br />other control systems.
<br />47. Unit Price Work—Work to be paid for on
<br />the basis of unit prices.
<br />48. Work—The entire completed onstruction
<br />or the various separately identifiable part . thereof re-
<br />quired to be provided under the Contract Documents.
<br />Work includes and is the result of p=rforming or
<br />providing all labor, services, and do umentation
<br />necessary to produce such cons ction, and
<br />furnishing, installing, and incorporating .:II materials
<br />and equipment into such construction, all as required
<br />by the Contract Documents.
<br />49. Work Change Directiv- A written
<br />statement to CONTRACTOR issued on or after the
<br />Effective Date of the Agreement and signed by
<br />OWNER and recommended by ENGINE R ordering
<br />an addition, deletion, or revision in th- Work, or
<br />responding to differing or unforeseen s bsurface or
<br />physical conditions under which the W. rk is to be
<br />performed or to emergencies. A Work Change
<br />Directive will not change the Contract "rice or the
<br />Contract Times but is evidence that the p- riles expect
<br />that the change ordered or documented by a Work
<br />Change Directive will be incorporated i a subse-
<br />quently issued Change Order following neotiations by
<br />the parties as to its effect, if any, on the Contract Price
<br />or Contract Times.
<br />50. Written Amendment -A writte statement
<br />modifying the Contract Documents, signed by
<br />OWNER and CONTRACTOR on or after e Effective
<br />Date of the Agreement and normally dea ing with the
<br />non -engineering or nontechnical rather han strictly
<br />construction -related aspects of the Con ract Docu-
<br />ments.
<br />1.02 Terminology
<br />A. Intent of Certain Terms or Adjecti
<br />1. Whenever in the Contract Do
<br />terms "as allowed," "as approved," or t
<br />effect or import are used, or the
<br />"reasonable," "suitable," "acceptable
<br />"satisfactory," or adjectives of like effe
<br />are used to describe an action or dete
<br />ENGINEER as to the Work, it is intend
<br />action or determination will be solely to
<br />general, the completed Work for com
<br />the requirements of and information in
<br />Documents and conformance with
<br />concept of the completed Project as a
<br />s
<br />uments the
<br />mis of like
<br />adjectives
<br />" "proper,"
<br />t or import
<br />ination of
<br />d that such
<br />evaluate, in
<br />• Hance with
<br />e Contract
<br />the design
<br />functioning
<br />whole as shown or indicated in the Contract
<br />Documents (unless there is a specifi statement
<br />indicating otherwise). The use of any uch term or
<br />adjective shall not be effective to assi n to ENGI-
<br />00700 - General Condition REV 5-10-13.doc
<br />00700 - 7
<br />F:1Public Works\ENGINEERING DIVISION PROJECTS\1314-107th Ave Milling90th St to 94th St\Admin\bid documents\Master Contract Documents\00700 - General Co
<br />13.doc
<br />ditions REV 5-10-
<br />
|