B. Nothing in this paragraph 12.06 bars a 3—yrs on"epwise speGifiGally PF(Wi ed
<br /> change in Contract Price pursuant to this Article 12 to the Contra6t DGGUmerts.
<br /> compensate CONTRACTOR due to delay,
<br /> interference, or disruption directly attributable to C. If Laws or Regulations of any public body
<br /> actions or inactions of OWNER or anyone for whom having jurisdiction require any Work (or part thereof)
<br /> OWNER is responsible. specifically to be inspected, tested, or approved by an
<br /> employee or other representative of such public body,
<br /> CONTRACTOR shall assume full responsibility for
<br /> ARTICLE 13-TESTS AND INSPECTIONS; arranging and obtaining such inspections, tests, or
<br /> CORRECTION, REMOVAL OR ACCEPTANCE OF approvals, pay all costs in connection therewith, and
<br /> DEFECTIVE WORK furnish ENGINEER the required certificates of inspec-
<br /> tion or approval.
<br /> 13.01 Notice of Defects D. CONTRACTOR shall be responsible for
<br /> arranging and obtaining and shall pay all costs in
<br /> A. Prompt notice of all defective Work of which connection with any inspections, tests, or approvals
<br /> OWNER or ENGINEER has actual knowledge will be required for OWNER's and ENGINEER's acceptance
<br /> given to CONTRACTOR. All defective Work may be of materials or equipment to be incorporated in the
<br /> rejected, corrected, or accepted as provided in this Work; or acceptance of materials, mix designs, or
<br /> Article 13. equipment submitted for approval prior to
<br /> CONTRACTOR's purchase thereof for incorporation
<br /> 13.02 Access to Work in the Work. Such inspections, tests, or approvals
<br /> shall be performed by organizations acceptable to
<br /> A. OWNER, ENGINEER, ENGINEER's Con- OWNER and ENGINEER.
<br /> sultants, other representatives and personnel of
<br /> OWNER, independent testing laboratories, and E. If any Work (or the work of others) that is to
<br /> governmental agencies with jurisdictional interests will be inspected, tested, or approved is covered by CON-
<br /> have access to the Site and the Work at reasonable TRACTOR without written concurrence of ENGI-
<br /> times for their observation, inspecting, and testing. NEER, it must, if requested by ENGINEER, be uncov-
<br /> CONTRACTOR shall provide them proper and safe ered for observation.
<br /> conditions for such access and advise them of
<br /> CONTRACTOR's Site safety procedures and F. Uncovering Work as provided in paragraph
<br /> programs so that they may comply therewith as 13.03.E shall be at CONTRACTOR's expense unless
<br /> applicable. CONTRACTOR has given ENGINEER timely notice
<br /> of CONTRACTOR's intention to cover the same and
<br /> 13.03 Tests and Inspections ENGINEER has not acted with reasonable prompt-
<br /> ness in response to such notice.
<br /> A. CONTRACTOR shall give ENGINEER timely
<br /> notice of readiness of the Work for all required 13.04 Uncovering Work
<br /> inspections, tests, or approvals and shall cooperate
<br /> with inspection and testing personnel to facilitate A. If any Work is covered contrary to the written
<br /> required inspections or tests. request of ENGINEER, it must, if requested by ENGI-
<br /> NEER, be uncovered for ENGINEER's observation
<br /> B. and replaced at CONTRACTOR's expense.
<br /> B. If ENGINEER considers it necessary or
<br /> advisable that covered Work be observed by ENGI-
<br /> NEER or inspected or tested by others, CONTRAC-
<br /> TOR, at ENGINEER's request, shall uncover, expose,
<br /> or otherwise make available for observation, inspec-
<br /> below; tion, or testing as ENGINEER may require, that
<br /> portion of the Work in question, furnishing all neces-
<br /> sary labor, material, and equipment. If it is found that
<br /> tests or inspeGtiGRS Gend!UGted pursuant to such Work is defective, CONTRACTOR shall pay all
<br /> paFagFaph 12 n4'R shall be paid as prGvided Claims, costs, losses, and damages (including but not
<br /> limited to all fees and charges of engineers, architects,
<br /> attorneys, and other professionals and all court or
<br /> 00700-General Conditions REV 5-10-13
<br /> 00700-36
<br /> F:\Public Works\ENGINEERING DIVISION PROJECTS\1049-8th St Sidewalk Improvements(58th Ave to 21st Court)Wdmim\bid dournents\LM DocumentsWaster Contract
<br /> Documents\00700-General Conditions REV 5-10-13.doc
<br />
|