Proposal for Materials Testing Services (Revised 8-29-14) <br />Old Dixie Highway Resurfacing v. Indian River County, Florida <br />August 29, 2014 cd Dunkelberger Proposal No PHB 140131 <br />Page 2 <br />Earthwork — Embankment and LBR 40 Shoulder Stabilization <br />• Laboratory Proctors (AASHTO T-99 and T-180) to determine maximum density of the <br />soils used for embankment and pipe backfill. <br />• In-place density tests of the embankment and pipe backfill at a frequency of 1 test per <br />500 linear feet each side of roadway (or fraction thereof) <br />• Limerock Bearing Ratio (LBR) tests of the in-place LBR materials for the Stabilized <br />Shoulders at a frequency of 1 test about every 2000 linear feet or 5 LBR samples on <br />each side of roadway (total of 10 tests) <br />• Thickness verification of completed 12" LBR Shoulder Stabilization. <br />• In-place density tests of the LBR Shoulder Stabilization at a frequency of 1 test per 500 <br />linear feet each side of roadway (total of 44 tests). <br />FDR Base Course <br />• FDR mix design — Review and evaluate the mix design developed by the Contractor for <br />its design approach and procedure. <br />• Full Sieve Analysis test on the virgin materials before injection of emulsion at a <br />frequency of 1 test every 1000 linear feet per lane (estimated total of 22 tests). <br />• Maximum Density (Proctor) tests of the in-place FDR base materials at a frequency of 1 <br />test every 1000 linear feet per lane (estimated total of 22 tests) <br />• In-place density tests at a frequency of 1 test per 500 linear feet per lane (estimated total <br />of 44 tests) <br />• Verification of completed FDR base course — Review and evaluate the verification <br />testing plan as well as the testing results as provided by the Contractor. <br />Contactor QC Testing of the Asphaltic Concrete (AC) Pavement <br />We understand that the Contractor is responsible for their own QC testing which shall include <br />performing at least one set of asphalt lab tests per day to evaluate the materials produced for <br />construction during paving. A minimum of three cores shall be cut by the Contractor on daily <br />basis to evaluate the in-place (constructed) density of the structural course construction <br />The cores shall be tested for bulk specific gravity, and the compaction will be evaluated based <br />on the percentage of the bulk specific gravity over the maximum density determined in the plant <br />on the bulk mix materials. As an option, the density (% compaction) of the wearing course <br />construction may be evaluated using a calibrated nuclear gauge if a correction factor can be <br />established using the core densities from the first day of wearing course paving. <br />Dunkelberger will not be in the asphalt plant to perform any verification testing (VT) during <br />asphalt production. <br />Field Observation <br />• Provide a full-time FDOT CTQP qualified technician to check the construction <br />operations for conformance with the applicable project specifications. <br />o FDR Construction — checking the depth of pulverization; checking the <br />homogeneity of the FDR virgin mix (without emulsion); checking the moisture <br />DUNKELBERGER <br />