Milestone Date <br /> Receive Authorization October 3,2017 <br /> Begin Design October 3,2017 <br /> 90%Design Submittal to SWDD November 17,2017 <br /> 90%TRC Meeting December 4,2017 <br /> Submit Permit Application December 8,2017 <br /> Final Design Submittal to SWDD January 5,2018 <br /> Receive Permits* February 6,2018 <br /> Draft Subtask 1.7 Technical Memorandum December 3,2017 <br /> Draft Subtask 1.8 Technical Memorandum December 3,2017 <br /> Final Subtask 1.7 Technical Memorandum 2 weeks from receipt of SWDD comments <br /> Final Subtask 1.8 Technical Memorandum 2 weeks from receipt of SWDD comments <br /> Advertise for Bids January 7,2018 <br /> Receive Bids February 6,2018 <br /> Award Contract February 21,2018 <br /> *Project schedule will be dependent on permitting and procurement activities.Schedule will be <br /> adjusted accordingly. <br /> PAYMENT AND COMPENSATION <br /> Compensation for this Amendment No. 1 to Work Order No. 1 described herein shall be made in <br /> accordance with the Contract between SWDD and CONSULTANT.The lump sum amount of this <br /> Amendment No. 1 for Tasks 1 thru 5 is$533,529; the not to exceed amount for Task 6 is$25,150; <br /> and the total not to exceed amount of Amendment No. 1 is$558,679.The new not to exceed Grand <br /> Total Amount of Work Order No. 1 is $690,499.CONSULTANT will submit monthly invoices for <br /> services rendered based on the percentage of work for each task completed for Tasks 1 thru 5.Task <br /> 6 will be invoiced based on a percentage of work complete as authorized by SWDD. <br /> For invoice purposes only,the value of each task in this Amendment No. 1 is as shown in the Table <br /> 1. <br /> Table 1 <br /> TASK VALUE FOR INVOICE PURPOSE—AMENDMENT NO. 1 TO WORK ORDER NO. 1 <br /> TASK DESCRIPTION VALUE <br /> 1 Meetings, Data Collection,Survey,and Geotechnical Investigation $28,440 <br /> 2 Project Quality Management $90,426 <br /> 3 Final Design, Drawings,Specifications,and Opinion of Probable <br /> Construction Cost Preparation $342,581 <br /> 4 Permitting Assistance $43,790 <br /> 5 Bidding Assistance $28,292 <br /> LUMP SUM SUBTOTAL AMOUNT= $533,529 <br /> 6 Additional Engineering Services—Not to Exceed $25,150 <br /> TOTAL AMENDMENT NO.1 TO WORK ORDER NO.1 NOT TO EXCEED= $558,679 <br /> WORK BREAKDOWN FOR FUNDING PURPOSES <br /> Segment 3 Cell 2 Expansion= $330,964 <br /> Segment 2 Partial Closure and LFG System Expansion= $227,715 <br />