ORDER NO. PSC-2018-0028-FOF-EI <br />DOCKET NO. 20180001 -EI <br />PAGE 9 <br />2027 <br />No Solar Resource Plan <br />2017-2018 Solar Resource Plan <br />2028 <br />1 -Year 20 MW PPA <br />298 MW Solar <br />2029 <br />1 Greenfield 3x1 CC Unit <br />1 -Year 287 MW PPA <br />2030 <br />Okeechobee 3x1 CC Unit; <br />1 -Year 155 MW PPA <br />1 Greenfield 3x1 CC Unit <br />2031 <br />Turkey Point 6 <br />Turkey Point 6 <br />2032 <br />Turkey Point 7 <br />Turkey Point 7 <br />2033 <br />Equalizing 599 MW CC <br />Equalizing 291 MW CC <br />Source: EXH 84 <br />FPL filed its 2017 Ten Year Site Plan in April 2017, which included for the first time the <br />Dania Beach Clean Energy Center. In August 2017, FPL filed revised testimony that updated its <br />evaluation of the 2017 and 2018 solar projects. Table 4 below is based on a new resource plan <br />incorporating both the FPL's revised filing and the addition of the Dania Beach Clean Energy <br />Center. <br />Table 4 <br />Revised Resource Plan <br />Year <br />No Solar Resource Plan <br />2017-2018 Solar Resource Plan <br />2017 <br />298 MW Solar <br />2018 <br />1 -Year 958 MW PPA <br />298 MW Solar; <br />1 -Year 636 MW PPA <br />2019 <br />Okeechobee 3x1 CC Unit; <br />1 -Year 155 MW PPA <br />Okeechobee 3x1 CC Unit <br />2020 <br />1 -Year 182 MW PPA <br />2021 <br />1 -Year 263 MW PPA <br />2022 <br />Dania Beach CC <br />Dania Beach CC <br />2023 <br />2024 <br />1 -Year 44 MW PPA <br />2025 <br />1 Greenfield 3x1 CC Unit <br />1 -Year 149 MW PPA <br />2026 <br />1 Greenfield 3x1 CC Unit <br />2027 <br />2028 <br />1 -Year 93 MW PPA <br />2029 <br />1 Greenfield 3x1 CC Unit <br />1 -Year 363 MW PPA <br />2030 <br />1 Greenfield 3x1 CC Unit <br />2031 <br />Turkey Point 6 <br />Turkey Point 6 <br />2032 <br />Turkey Point 7 <br />Turkey Point 7 <br />2033 <br />Equalizing 574 MW CC <br />Equalizing 266 MW CC <br />Source: EXH 87 <br />The revised resource plan shows that the addition of the 2017 and 2018 solar projects <br />should reduce FPL's need for purchased power agreements. <br />In completing the analysis, FPL considered multiple components to determine cost <br />effectiveness: solar revenue requirements, avoided generation costs, and avoided system costs. <br />For the proposed solar facilities, the revenue requirements included fixed operation and <br />maintenance (O&M), equipment, installation, land cost, and transmission interconnection cost. <br />