INDIAN RIVER COUNTY, FLORIDA <br />BOARD MEMORANDUM <br />TO: Jason E. Brown, <br />County Administrator <br />THROUGH: Richard B. Szpyrka, P.E. <br />Public Works Director <br />FROM: James D. Gray, Jr. <br />Natural Resources Manager <br />SUBJECT: Work Order No. 2018029-1 APTIM Environmental & Infrastructure, Inc <br />Sector 5 Beach and Dune Restoration Project — Pre -Construction Services <br />DATE: April 16, 2018 <br />BACKGROUND <br />On April 3, 2018, the Board approved a contract with Aptim Environmental & Infrastructure, Inc. <br />(Aptim) for professional coastal engineering and biological support services related to the <br />management and restoration of the Sector 5 (City of Vero Beach) beach project area. <br />The Sector 5 project area is a 3 mile section of shoreline that extends just north of Tracking Station <br />Beach Park south to the Gables Oceanfront Condominiums. The majority of the project area is <br />located within the City of Vero Beach's jurisdiction with the exception of Tracking Station Park and <br />the Florida Tech Marine Lab residing in unincorporated Indian River County. <br />DESCRIPTION AND CONDITIONS <br />The proposed Work Order No. 2018029-1 includes seven (7) separate tasks and provides <br />professional engineering services for the continued development and implementation of the <br />planned Sector 5 Beach and Dune Restoration Project. Specifically, Work Order No. 2018029-1 <br />addresses pre -construction phase services required for permitting and development of <br />construction plans and specifications. <br />Work Order No. 2018029-1 is for a lump sum amount of $212,462.95. Note: Given the expected <br />project fill volumes, Sector 5 is being designed as a truck haul (Upland Mine) fill project. However, <br />an optional task (Task 7 — Include Offshore Borrow Area as Sand Source), totaling $19,877, is <br />included in this work order in the event permits need to be modified to include an offshore sand <br />source. Considering the similar project development schedule, it may be conceivable to utilize <br />the same offshore borrow source for multiple other concurrent projects (Sector 3 and Sector 7) <br />also currently under design and permitting. If the offshore source is determined not necessary, <br />the total amount of Work Order No. 2018029-1 will be reduced by $19,877. <br />C:\Users\legistarWppData\Local\Temp\BCL Technologies\easyPDF 8\@BCL@840D3BAA\@BCL@840D3BAA.docx 56 <br />