Page 2 <br />BCC Agenda Item <br />June 19, 2018 <br />Task 2: Summer 2018 Sector 7 Post Construction Monitoring (R -97-R-108) <br />In the spring of 2007, the County completed construction of the Sector 7 Beach Restoration <br />Project. The County has completed all Permit required post construction monitoring for the <br />Sector 7 Project. However, hydrographic surveys of the project area have continued <br />semiannually to determine the long term performance of the project. Task 2 includes all <br />surveying (2 miles) required to continue the annual monitoring of the Sector 7 Beach <br />Nourishment Project. Task 2 totals a lump sum amount of $6,600. <br />Task 3: Summer 2018 Countywide Beach Monitoring (R-61— R-96 and R -109-R-119) <br />For the shoreline outside of the Sector 3 and Sector 7 beach projects, countywide beach profile <br />surveys are necessary to identify areas of chronic beach erosion and determine if infrastructure <br />may be vulnerable to storm damage. The beach profile surveys will then be used to determine <br />appropriate projects to mitigate erosion as identified in the County Beach Preservation Plan, <br />including the upcoming Sector 5 Beach Restoration Project. Task 3 includes the remaining <br />countywide (9 miles) beach profile surveys. Task 3 totals a lump sum amount of $25,850. <br />Please note: <br />The Sebastian Inlet District (District), as part of their Inlet Management Plan, conducts <br />semiannual beach profile surveys along the northern 5.6 miles of the County. The District <br />continues to partner with the County and has agreed to provide their certified 2018 beach profile <br />survey data (winter and summer) to the County, resulting in a complete 22.4 mile countywide <br />(semiannual) beach profile survey and a combined annual savings of approximately $30,000 to <br />the County. <br />The aggregate of Tasks 1-3 under Work Order No. 7 totals a lump sum amount of $57,750. <br />FUNDING <br />Local funding of Beach Restoration includes a portion of Local Option Tourist Tax Revenue as well <br />as allocation of the One Cent Sales Tax. Funding for Work Order No. 7 will be provided from <br />three (3) separate accounts. <br />Task 1: Summer 2018 Sector 3 Beach and Dune Restoration Proiect Post Construction Monitoring <br />Survey(R-15-R-60) <br />Funding for Task 1 is budgeted and available for monitoring of the Sector 3 Beach Restoration <br />Project in the Beach Restoration Fund, Sector 3 Beach Post Construction Monitoring Account No. <br />12814472-033490-05054. Task 1 totals a lump sum amount of $25,300. <br />Task 2: Summer 2018 Sector 7 Post Construction Monitoring (R -97-R-108) <br />Funding for Task 2 is budgeted and available for monitoring of the Sector 7 Beach Restoration <br />Project in the Beach Restoration Fund, Sector 7 Beach Preservation Monitoring Account No. <br />12814472-033490-05079. Task 2 totals a lump sum amount of $6,600. <br />C:\Users\legistar\AppData\Local\Temp\BCL Technologies\easyPDF 55 <br />8\@BCL@CC3 8EAC3\@BCL@CC3 8EAC3.docx <br />