Laserfiche WebLink
4.01 Time of the Essence <br />A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final <br />payment as stated in the Contract Documents are of the essence of the Contract. <br />4.02 Days to Achieve Substantial Completion, Final Completion and Final Payment <br />A. The Work will be substantially completed on or before the 148180th calendar day after the date when <br />the Contract Times commence to run as provided in paragraph 2.03 of the General Conditions, and <br />completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions on or <br />before the 4-59 210th calendar day after the date when the Contract Times commence to run. <br />SECTION 550 — Notice to Proceed <br />You are notified that the Contract Times under the above contract will commence to run on . By that <br />date, you are to start performing your obligations under the Contract Documents. The contract has <br />allocated 428 180 calendar days for Substantial Completion of this project and 1-59 210 calendar days for <br />Final Completion. In accordance with Article 4 of the Agreement the date of Substantial Completion is <br />and the date of readiness for final payment is <br />Question 4. Building Elevation on sheet A5.1 shows 8 lites to the left of door 151. The floor plan shows 7. Which is <br />correct? <br />Answer: There are seven panels of storefront between Door 151 and the solid wall panel by Door 1018. The East <br />Elevation on Sheet A5.1 will be revised accordingly in the Released for Construction plan set. <br />Question 5. Are wood doors factory or field finished? <br />Answer: The wood doors are factory finish. Alternatively, the millwork subcontractor may shop -finish both the <br />doors and the micro -perforated wood veneer acoustical panels to the standard in the specifications. Field finish on <br />site is not acceptable. <br />Question 6. What is the RAF fascia panel? <br />Answer: The RAF fascia panel is the raised access flooring manufacturer's standard closure for vertical faces that <br />are not against a conventionally -constructed wall. In this project, they are only used in the Clerk of Court and <br />Utilities areas where the ramp cuts through the access flooring on one side. The fascia panels should be used <br />between the ramp and the adjacent access flooring, and at the vertical face of the platform that continues to the <br />wall west of the raised area. This allows for enclosure of the cabling route from the IT Room. <br />Question 7. We need some idea as to wall covering due to a large variation in price. <br />Answer: Allow $30 per yard for vinyl wallcovering (material cost only). <br />Question 8. Will alkyd Dryfall paint be acceptable for exposed structure ceilings? <br />Answer: Alkyd dry fall paint will be acceptable, in semi -gloss, for the overhead exposed structure, hangers, and <br />underside of roof deck. <br />Question 9. Are electric locks required or will electric strikes be acceptable. There is a significant cost difference. <br />Answer: 1. Door hardware on doors with access control devices will be coordinated with the County's security <br />team, project manager, architect, contractor and hardware subcontractor. County to provide electronic devices to <br />read key fob (or other security ID) to unlock doors with hardware groups 4, 5, 7, and 8. Contractor to route power <br />to same. As County has not yet specified their selected hardware, Contractor shall provide pricing information for <br />the more costly option. Price the coordinating door hardware and power/data supply option which will be more <br />costly. <br />Page 2 of 4 <br />