SECTION 01 14 00 <br /> WORK RESTRICTIONS <br /> GENERAL <br /> 1.01 SECTION INCLUDES <br /> A. Administrative and procedural requirements for work sequence, work restrictions, <br /> occupancy requirements and use of premises. <br /> 1.02 WORK SEQUENCE <br /> A. The Work shallbe conducted in the following sequences unless construction phases are <br /> otherwise specified. <br /> 1. Construct Work in phases to accommodate the Owner's use; if applicable, of the <br /> premises during the construction period; coordinate the construction schedule <br /> and operations with the Owner and Engineer. <br /> 2. Construct the Work in phases to provide for public convenience. Do not close <br /> off public use of facility until completion of one phase of construction will <br /> provide alternative usage. <br /> 3. Construction shall be scheduled in such a manner that once work has commenced <br /> on one facility, the Contractor's work force shall remain at that facility <br /> continuously each work day through final completion at that facility. <br /> 1.03 OCCUPANCY REQUIREMENTS <br /> A. Owner Occupancy <br /> P Y <br /> 1. Owner will occupy the premises during the entire period of construction to <br /> conduct normal operations. Cooperate with Owner in all construction operations <br /> to minimize conflict,and to facilitate Owner usage. <br /> 2. Contractor shall at all times conduct his operations as to ensure the least <br /> inconvenience and the greatest amount of safety and security for the Owner, his <br /> staff,and the general public. <br /> 3. Control noise from operations so that building occupants are not affected. <br /> 4. Control odors from air intakes so that building occupants are not affected. <br /> 1.04 USE OF PREMISES <br /> A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of <br /> site beyond areas in which the Work is indicated. <br /> 1. Limits: Confine constructions operations to areas of work being renovated as <br /> approved by Engineer and Owner. <br /> 2. Driveways and Entrances: Keep driveways and entrances serving premises clear <br /> and available to Owner,Owner's employees,and emergency vehicles at all times. <br /> Do not use these areas for parking or storage of materials. <br /> a. Schedule deliveries to minimize use of driveways and entrances. <br /> b. Schedule deliveries to minimize space and time requirements for storage <br /> of materials and equipment on-site. <br /> 3. Move any stored materials and equipment that interfere with operations of the <br /> Owner. <br /> Sebastian Corners Roof Replacement 01 14 00-1 Work Restrictions <br />