Laserfiche WebLink
Consultant will review bids, provide a summary of comments, and a letter that identifies <br />the lowest responsive, responsible bidder. <br />TIME SCHEDULE <br />Consultant will conduct Task 1 within 2 - 4 weeks and Task 2 within 6 — 8 weeks from <br />notice to proceed. Task 3 is scheduled to be 2 — 4 weeks after task 2 is complete. <br />Bidding phase is assumed to take up to 4 — 6 weeks after task 1 through 3 are complete. <br />FEE SCHEDULE <br />We will provide these services in accordance with our extension and amendment of our <br />Continuing Consulting Engineering Services Agreement for Professional Services dated <br />April 17th, 2018, by and between INDIAN RIVER COUNTY, a political subdivision of <br />the State of Florida ("COUNTY") and Kimley-Horn and Associates, Inc., <br />("Consultant"). <br />The Consultant will provide professional services for Task 1 through Task 4 on a lump <br />sum fee basis as follows: <br />Task No. <br />Task <br />Task Fee <br />Task 1 <br />Condition Assessment <br />$ 15,827 <br />Task 2 <br />Prepare Documents <br />$ 39,100 <br />Task 3 <br />Permitting <br />$ 7,715 <br />Task 4 <br />Bidding Phase <br />$ 9,724 <br />Total Lump Sum Fee = <br />$ 72,366 <br />ADDITIONAL SERVICES <br />The following services are not included in the Scope of Services for this project, but may <br />be required depending on circumstances that may arise during the execution of this <br />project. Additional services include, but may not be limited to the following: <br />• Membrane pilot testing is not included under this scope <br />• Direct purchase of membrane elements and the procurement of these elements is <br />not included under this scope, but can be provided if decided to purchase <br />membrane elements directly <br />• Design drawings of any modification to the RO skids beyond what is listed herein <br />• Construction phase services not included under this task order, but will be <br />prepared depending on schedule of bidding. <br />C:\Users\mark.miller\Documents\IRCU\Oslo Membrane R&R\Oslo WTP Membrane Replacement 10.4.2018.docx <br />Page 4 of 4 <br />