Question 6. When is the project expected to be awarded, or go to commission? Is there a set deadline for <br />the final completion or specific start date? <br />Answer: There is no set start date, however the anticipated award date is August 14, 2018, and Notice to <br />Proceed is typically around two weeks after award. The duration of the project is 60 days following NTP. <br />Question 7. On the plan pages it calls out type e curb and gutter, where on other pages it says existing <br />curb; can we conclude that all curbing is existing or is the new curb and gutter proposed? <br />Answer: All calls refer to existing curb and gutter. There is no new curb and gutter associated with the <br />project. <br />Question 8. In the ITB on page 15 it says the contractor should use the form AIA Document A310 for the <br />bid bond. I did not see this document in the ITB. Where can I download the correct form? <br />Answer: "AIA Document A310 Bid Bond" should be available through your bonding company. Please <br />consult with them. <br />********This Addendum MUST be acknowledged where indicated on the Bid Form and/or by return of <br />this page with your proposal********* <br />Company Name t'��� C)ns jl'tu Ui'1 <br />Name: �' '!.l�1'<<: h/1CL Title: ice' S C lt. <br />(Type / Printed) <br />`` <br />Authorized Signature: � ,i.�Ct% �'�-- —Date: <br />i <br />7 r <br />Telephone << f �(�� 7 f% Fax: <br />Page 2of2 <br />