Laserfiche WebLink
EXHIBIT C (TIME SCHEDULE) <br />SECTION 3 SCHEDULE & DELIVERABLES <br />The following schedule is anticipated for Tasks 1 through 6: <br />A. Fifty-six calendar days from NTP: <br />• Task 1 — Survey, <br />• Task 2 — Pavement Cores, <br />• Task 6 — Notice to Utility Providers. <br />B. Twenty-one calendar days from completion of survey and pavement cores: <br />• Task 3 - Existing conditions review and list, meeting with IRC Staff. <br />C. Fifty-six calendar days from completion of Task 3 Existing Conditions Review: <br />• Task 4 - Roadway Plans — 60% design completion, <br />• Task 5 - Signalization Plans — 60% design completion, <br />• Task 6 - Submittal of 60% Design Documents to County, <br />• Task 6 - Submittal of SJRWMD Permit Exemption Request. <br />ATKINS <br />D. Twenty-one calendar days from submittal of 60% Phase II Design Documents to County: <br />• Review comments by County. <br />E. Twenty-eight calendar days from receipt of County comments: <br />• Task 4 - Roadway Plans — 90% design completion, <br />• Task 5 - Signalization Plans — 90% design completion, <br />• Task 6 - Submittal of 90% Construction Documents to County and FDOT. <br />F. Twenty-one calendar days from submittal of 90% Construction Documents to County: <br />• Final review comments by County. <br />• Review comments from FDOT. <br />G. Twenty-one calendar days from receipt of County and FDOT comments: <br />• Task 4 - Roadway Plans —100% Final Construction Documents, <br />• Task 5 - Signalization Plans —100% Final Construction Documents, <br />• Task 6 - Submittal of Phase 100% Construction Documents to County and FDOT. <br />February 14, 2019 <br />Page 8of10 <br />