Task 1.1- Existing Sewer Infrastructure Assessment <br />Consultant will assess CCTV video of the previously unsurveyed 2,500 LF of <br />existing gravity mains provided by IRCU. Pipe defects will be recorded utilizing a <br />standardized coding system in accordance with the National Association of Sewer <br />Service Companies (NASSCO) Pipeline Assessment and Certification Program <br />(PACP). <br />Task 1.2 - Report and Recommendations <br />Consultant will develop a report identifying and prioritizing deficiencies according <br />to NASSCO standards. <br />Consultant will evaluate options for correcting the defects within the system, <br />including but not limited to point repairs, joint repairs, lining of existing pipe, and <br />full pipe replacement. <br />Consultant will make recommendations for improvements to the system based on <br />the findings and will provide an Opinion of Probable Cost (OPC). The design of the <br />recommendations is not included in this contract. <br />The OPC from the Phase 1 Ixora Park SSES will be appended to include these Phase <br />2 SSES costs, providing a comprehensive OPC for the full Ixora Park sewer <br />rehabilitation. <br />The Consultant will provide a draft copy of the report in PDF format to IRCU and <br />will hold a meeting with IRCU to review the results if required. A hard copy and a <br />PDF copy of the final report will be provided to IRCU for a final deliverable. <br />TASK 2 -PIPE LINING AND LATERAL REHABILITATION <br />Approximately 4,100 LF of gravity sewer pipe was recommended to be cleaned and <br />lined using cast -in-place pipe (CIPP) and nine laterals on these pipes were <br />recommended for rehabilitation. The pipes recommended to be lined are indicated <br />on Figure 1. The Consultant will prepare design specifications for the pipe lining <br />and lateral rehabilitation work to be completed. <br />The Consultant will prepare one set of bid documents for pipe lining and one set of <br />bid documents for lateral rehabilitation. Consultant will provide up to three (3) <br />F:\Utilities\UTILITY - Engineering\Projects - Capital Projects\19-0607 Ixora Park\Admin\Ixora Rehab Scope.docx Page 2 of 4 <br />