Page 3 of 3 <br />Q. Overbuild should be in tonnage not square yards. <br />A. The Itemized Bid Schedule and Technical Specifications have been changed to tons. <br />Q. There is no miscellaneous asphalt shown under the guardrail or accounted for on the <br />bid form. <br />A. The plans have been revised to show asphalt under the guardrail and Item No. 339-1 <br />has been added to the Summary of Quantities and the Itemized Bid Schedule. <br />Q. What is the anticipated start date? <br />A. Within a month of the bid opening, depending on BCC meeting schedule. <br />Q. Is the embankment required to slope away from the IRFWCD canal per permit <br />requirements? <br />A. The 1 -foot bench is to slope toward the back of curb, then tie into existing with <br />minimal disturbance to the existing ground. <br />Q. Will the current construction project at 43rd Avenue be completed by the time of NTP <br />on this project? <br />A. Hopefully, but if not, there will have to be some coordination between contractors. <br />Q. Will we be required to submit certified payroll? <br />A. No. <br />Meeting Adjourned. <br />F:\Public Works\ENGINEERING DIVISION:PROJECTS\141.4-49th St_58th Ave to 31st Ave\I-Admin \M.eetings\PreBid\I:RC- <br />141.4 PREBIDMINS 20I907I8.doc <br />