5.02 Pay Requests. <br /> A. On a form provided by the OWNER, each request for a progress payment shall contain <br /> the CONTRACTOR'S certification. All progress payments will be on the basis of progress <br /> of the work measured by the schedule of values established, or in the cane of unit price <br /> work based on the number of units completed. After fifty percent/ 0%) completion, <br /> and pursuant to Florida Statutes section 218.735(8)(d),the CONTRACTOR may submit a <br /> pay request to the County as OWNER for up to one half (1/2) th‘retainagerheideld by <br /> the County as OWNER, and the County as OWNER shall promptly make rm-ake parent to the <br /> CONTRACTOR unless such amounts are the subject of a good fait.,dli p,,ute;fthe subject <br /> of a claim pursuant to Florida Statutes section 255.05(2005);or otherwise the subject, f <br /> a claim or demand by the County as OWNER or the CONTRACTOR. The CONTRAefOR <br /> acknowledges that where such retainage is attributable to the labor, serrvrces, or <br /> materials supplied by one or more subcontract ro s`r suppliers, the CONTRAGTJ,ORshall <br /> timely remit payment of such retainage to th.o.se subcontractors and suppliers. Pursuant <br /> to Florida Statutes section 218.735(8)(c).(2005) CONTRACTOR further aCnowledges and <br /> agrees that: 1) the County as OWN'E, hall�receivie immediate\to written notice of all <br /> decisions made by CONTRACTOR tdwithhold retainage on any subcontractor at greater <br /> than five percent (5%) after fifty percent (50%)`completion; and/2) CONTRACTOR will <br /> not seek release from the County as.OWNER the withheld retainage until the final pay <br /> request. \.7 <br /> 5.03 Paragraphs 5.01 and 5.02 do not apply to c nstruction ervices work purchased by the County <br /> as OWNER which are paid for, in whole or in\partw,ikederal`fu.,n?1s and are subject to federal grantor <br /> laws and regulations or requi�nents that arre contrary\to any provision of the Local Government <br /> Prompt Payment Act. In such event, aymenrtt nd reta mage provisions shall be governed by the <br /> applicable grant requirementsu <br /> nddelines. <br /> 5.04 Accepts Final Payment`as Re <br /> Cof. lease. <br /> A. The-ccept�''7.the CONTRACTOR of final payment shall be and shall operate as a <br /> releas to thOWNER ro,m all claims and all liability to the CONTRACTOR other than <br /> clam, inzisted amounts as may be specifically excepted by the CONTRACTOR for all <br /> things\done or furnished in connection with the work under this Agreement and for <br /> every act'and neglect of the OWNER and others relating to or arising out of the work. <br /> Anyypaymen1, however, final or otherwise, shall not release the CONTRACTOR or its <br /> sur-retres from any obligations under this Agreement, the Invitation to Bid or the Public <br /> Construction Bond. <br /> ARTICLE,6—PU.BUC,CONSTRUCTION BOND <br /> (4.,..:-._—:„.„.",.- <br /> 6.01 <br /> 4.,..:`J'6.01 Within fifteen (15)days of receipt of the Contract Documents for execution,the CONTRACTOR <br /> shall furnish a Public Construction Bond in an amount equal to 100%of the Contract Price. If bid <br /> does not exceed$100,000, no Public Construction Bond will be required. <br /> A. In lieu of the Public Construction Bond,the CONTRACTOR may furnish an alternative form of <br /> security in the form of cash, money order,certified check,cashier's check, irrevocable letter of <br /> credit or a security as listed in Part II of F.S. Chapter 625. Any such alternative form of security <br /> 26 <br />