Laserfiche WebLink
Consultant will review bids and prepare a bid review letter that identifies the lowest, most <br />responsive and responsible bidder. <br />SCHEDULE <br />In general, the following schedule is anticipated and consultant will work as expeditiously as <br />possible to meet it: <br />Task 1 10 - 12 weeks from Notice to Proceed (NTP) <br />Task 2 3 - 4 weeks after Task 1 <br />ADDITIONAL SERVICES <br />The following services are not included in the Scope of Services for this project but may be <br />required depending on circumstances that may arise during the execution of this project. <br />Additional services include, but may not be limited to the following: <br />• Design phase services beyond those described herein <br />• Design improvements to Motor Control Center (MCC) <br />• Additional design meetings <br />• Construction phase services <br />FAUtilities\UTILITY - EMPLOYEE FOLDERS\Terry Southard\Memos\2020.01.22 - Scope - Oslo ATS (002).docx Page 2 of 4 <br />