EXHIBIT C — TIME SCHEDULE <br />This Task Order shall commence upon Notice to Proceed with the work to be completed as <br />follows: <br />Kick off meeting (NTP) <br />Alternatives Evaluation 3 weeks <br />County Determination of Option 3 Weeks <br />Relocation Project <br />Topographic Mapping <br />4 weeks <br />Utility Locates and potholing <br />(Concurrent with survey) <br />Design to 60% & Meeting <br />3 weeks <br />Permitting, Design to 90% & Submit <br />3 weeks <br />County Review <br />3 weeks <br />Respond to Comments <br />1 weeks <br />Final Bid Docs and Deliver <br />1 weeks <br />Total <br />21 Weeks <br />147 Calendar Days <br />The above schedule assumes reasonable response times from the permitting agencies. <br />