Laserfiche WebLink
EXHIBIT `3' <br />TIME SCHEDULE <br />WORK ORDER NO.2 <br />Time of Performance <br />The estimated time frame for completion of services from the approval of this Work Authorization is a follows: <br />1. Surveying, Engineering Design & Preparation of 4'/z Months <br />Construction Plans, specifications and Bid Documents <br />2. Submittal of Permit Applications and Receipt of permits 1 Month <br />And Bidding/Contract Award (Done Concurrently) <br />3. Construction 5 Months <br />Remainder of Page Intentionally Left Blank <br />