IRC -2022 <br />on the part of OWNER to exercise this right for .the benefit of CONTRACTOR, any <br />Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee <br />or agent of any of them. <br />SC -13.07 Correction Period <br />SC -13.07 A. Delete the firstsentence of paragraph GC -13.07.A in its entirety and insert the following sentence <br />in its place <br />A. If within one year after the date of Final Completion or such longer period of time as may <br />be prescribed by Laws or Regulations or by the terms of any applicable special guarantee <br />required by the Contract Documents or by any specific provision of the Contract <br />Documents, any Work is found to be defective, or if the repair of any damages to the land <br />or areas made available for CONTRACTOR's use by OWNER or permitted by Laws and <br />Regulations as contemplated in paragraph 6.11.A is found to be defective, CONTRACTOR <br />shall promptly, without cost to OWNER and in accordance with OWNER's written <br />instructions: (i) repair such defective land or areas, or (ii) correct such defective Work or, if <br />the defective Work has been rejected by OWNER, remove it from the Project and replace it <br />with Work that is not defective, and (iii) satisfactorily correct or repair or remove and <br />replace any damage to other Work, to the work of others or other land or areas resulting <br />therefrom. <br />SC -13.07 B. Delete paragraph GC -13.07.8 in its entirety and insert the following sentence in its place <br />B. In special circumstances where a particular item of equipment is placed in continuous <br />service before Final Completion of all the Work, the correction period for that item may <br />start to run from an earlier date if so provided in the Specifications or by Written <br />Amendment. <br />SC -14.02 Progress Payments <br />SC -14.02.13.5. Delete paragraph GC -14.02.8.5.d in its entirety and insert the following paragraph in its place: <br />d. ENGINEER has actual knowledge of the occurrence of any of the events enumerated in <br />paragraph 15.02.A; or <br />SC -14.02.13.5. Add the following sentences at the end of paragraph GC -14.02.8.5: <br />e. OWNER has been required to pay ENGINEER additional compensation because of <br />CONTRACTOR delays or rejection of defective Work; or <br />f. OWNER has been required to pay an independent testing laboratory for subsequent <br />inspections, tests, or approvals taken after initial failing inspections, tests, or approvals. <br />SC -14.02.C.1. Delete paragraph GC -14.02.C.1 in its entirety and insert the following <br />paragraph in its place: <br />C. Payment Becomes Due <br />Supplementary Conditions - 00800-9 <br />FAPublic Works\ENGINEERING DIVISION PROJECTS\2022 4th St Culvert Replacement at 90th Ave\1-Admin\Bids\Bid Documents\DIV 0 5 Conditions of the Contract - <br />20201118.docx — — <br />