EXHIBIT B
<br /> FEE SCHEDULE
<br /> The Consultant will provide these services in accordance with our Continuing Consulting Engineering Services Agreement for
<br /> Professional Services dated May 18, 2021, by and between INDIAN RIVER COUNTY, a political subdivision of the State of
<br /> Florida("COUNTY")and Kimley-Horn and Associates, Inc., ("Consultant").
<br /> Amendment No. 1 will increase the original authorization by a lump sum fee of$40,830, for an amended Work Order Total of
<br /> $267,250,as detailed below. Individual task amounts are informational purposes only.All permitting, application, and similar
<br /> project fees will be paid directly by the County.
<br /> Subs
<br /> Senior Senior
<br /> Project Civil Civil Senior Accounting/ KHA Labor Amendment Original Amended
<br /> Manager Engineer Engineer Designer Admin Subtotal Geotech Total Authorization Total
<br /> Task 1-Landfill Gas Pipeline Design 38 4 0 0 0 $ 9,450 , $ 1,750 $ 11,200 $ 91,780 $ 102,980
<br /> 1.1 Preliminary Design Services
<br /> 1.1.1-Alignment for Survey Purposes 0 0 0 0 0 $ - $ - $ - $ 3,320 $ 3,320
<br /> 1.1.2-Survey 0 0 0 0 0 $ - $ - $ - $ 3,110 $ 3,110
<br /> 1.1.3-Geotech 2 0 0 0 0 $ 450 $ 1,750 $ 2,200 $ 2,900 $ 5,100
<br /> 1.2 Landfill Gas Pipeline Design $ -
<br /> 1.2.1-30%Design 0 0 0 0 0 $ - $ - $ - $ 8,420 $ 8,420
<br /> 1.2.2-60%Design 0 0 0 0 0 $ - $ - $ - $ 18,010 $ 18,010
<br /> 1.2.3-90%Design and Final Bid
<br /> Package 0 0 0 0 0 $ - $ - $ - $ 9,890 $ 9,890
<br /> 1.2.4-Bidding and Project
<br /> Management 12 0 0 0 0 $ 2,700 $ - $ 2,700 $ 21,330 $ 24,030
<br /> 1.3 Coordination with Heartland 24 4 0 0 0 $ 6,300 $ - $ 6,300 $ 24,800 $ 31,100
<br /> Task 2-Landfill Gas Skid Design 36 10 46 8 4 $ 18,620 $ - $ 18,620 $ 134,640 $ 153,260
<br /> 2.1 Request for Information 0 0 0 0 0 $ - $ - $ - $ 9,210 $ 9,210
<br /> 2.2 30%Design 0 0 0 0 0 $ - $ - $ - $ 37,200 $ 37,200
<br /> 2.3 60%Design 0 0 0 0 0 $ - $ - $ - $ 29,650 $ 29,650
<br /> 2.4 90%Design and Final Bid Package 0 0 0 0 0 $ - $ - $ - $ 30,250 $ 30,250
<br /> 2.5 Bidding and Project Management 12 10 6 0 4 $ 6,180 $ - $ 6,180 $ 26,380 $ 32,560
<br /> 2.6 Permitting 24 0 40 8 0 $ 12,440 $ - $ 12,440 $ 1,950 $ 14,390
<br /> Task 3-SCADA Coordination and
<br /> Electrical Considerations 16 32 0 2 0 $ 11,010 $ - $ 11,010 $ - $ 11,010
<br /> TOTALS 90 46 46 10 4 $ 39,080 $ 1,750 $ 40,830 $ 226,420 $ 267,250
<br /> Page 5 of 7