My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
03/01/2022
CBCC
>
Meetings
>
2020's
>
2022
>
03/01/2022
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
4/5/2022 3:39:21 PM
Creation date
3/30/2022 2:08:00 PM
Metadata
Fields
Template:
Meetings
Meeting Type
BCC Regular Meeting
Document Type
Agenda Packet
Meeting Date
03/01/2022
Meeting Body
Board of County Commissioners
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
131
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
SECTION 00942 - Change Order Form <br />No. 002 <br />DATE OF ISSUANCE: 02/10/2022 EFFECTIVE DATE: 02/10/2022 <br />OWNER: Indian River County <br />CONTRACTOR Guettler Brothers Construct'on, LLC <br />Project: Phase 1 of the Sector 3 Beach and Dune Restoration Proiect <br />OWNER'S Bid No. 2021012 <br />You are directed to make the following changes in the Contract Documents: <br />Description: <br />Decrease the amount of additional sand delivered and placed under Amendment No. 1 by <br />41,953 cubic yards to reflect actual sand placed on project based on current surveys and <br />compliance with fill templates. <br />Decrease the Force Account Amount by $1,129,224.90 to account for un -used dollars in <br />that category. <br />Reason for Change Order: <br />Upon recommencement f construction, pre -construction surveys taken in the incomplete <br />portion of the Sector 3, Phase 1 project area identified a decrease in the amount of sand <br />needed to fill the project template. <br />Attachments: <br />Description of Itemized Changes <br />CHANGE IN CONTRACT <br />T <br />PRICE: <br />Description <br />Amount <br />Original Contract Price <br />$11.987.010.00 <br />$2.487.100.00 <br />Net Increase (Decrease) from <br />Contract Amendment No. 1 <br />Final Completion-, <br />Contract Price prior to this <br />$14.474.1 1x.00 <br />Change Order: <br />Amendment No. 1: <br />Net increase (decrease) of this <br />j$2 484 15_,801 <br />Change Order: <br />Final Completion: <br />Contract Price with all approved <br />Contract Time prior to this <br />$11.989,803.20 <br />Change Orders: <br />Substantial Completion: <br />CHANGE IN CONTRACT <br />T <br />TIMES <br />Description <br />Time <br />Original Contract Time: <br />(days or dates) <br />Substantial Completion: <br />116 days <br />Final Completion-, <br />130 days <br />Net change from Contract <br />Amendment No. 1: <br />(days) <br />Substantial Completion: <br />0 <br />Final Completion: <br />0 <br />i <br />Contract Time prior to this <br />Change Order: <br />(days or dates) <br />Substantial Completion: <br />116 days <br />_ Final Completion: <br />130 days <br />Net increase (decrease) this <br />Change Order: <br />(days or dates) <br />Substantial Completion: <br />0 <br />Final Completion: <br />0 <br />Contract Time with all <br />approved Change Orders: <br />(days or dates) <br />Substantial Completion: <br />116 days <br />Final Completion: <br />130 days <br />ACCEPTED: RECOMMENDED: <br />Eric Digitally signed by <br />Cha, <br />Eric Charest <br />B6AI�Z� BY Charest 2 359 050'00'7 <br />CONTRACTOR (Signature) ENGINEER (Signature) <br />Date_ 1 e 22Date: <br />APPROVED: <br />Richard B.�1A <br />.sron..�E. wwr <br />By: Szpyrka, P. E. <br />OWNER (Signature) <br />Date: <br />Change Order Form #2_22.0210.doc <br />00942-1 <br />F 1Pubtic Work3%ENGINEERL4G DIVISION PROJEC7S9925 Sector 3 Beadh mr-d Dune Restoration Protectil-Aft.40hange 0rder3lCO#ZCrtanga Order oc Form #2_22- <br />0210.dRev. 05101 ! <br />
The URL can be used to link to this page
Your browser does not support the video tag.