Laserfiche WebLink
Section 13 — Construction Schedule <br />The following schedule follows approval of the required Developer's Agreement. <br />• Months 1-6 <br />o Homebuyer outreach <br />o Design and permitting of infrastructure <br />o Subdivision platting <br />At completion of infrastructure permitting, and once a pool of potential <br />homebuyers is assembled, the next stage of the project will commence. <br />• Months 7-12 <br />o Infrastructure Construction <br />o Homebuyer qualification and counseling <br />o Final design and permitting of homes <br />At completion of infrastructure construction and homebuyer qualification and <br />counseling, buyers will be required to sign contracts for specific homes, and <br />construction financing will be secured. <br />o If permitted by the County, models would be constructed concurrent with <br />the infrastructure for marketing purposes. <br />Months 12-24 <br />o Homebuilding will be completed in phases with approximately 3-4 homes <br />being built at a time. <br />o Upon completion of construction and issuance of Certificate of <br />Occupancies by the County, home will close and transfer to the income - <br />qualified and/or first-time homebuyer. <br />Please see construction schedule details below: <br />136 <br />