Laserfiche WebLink
Change Order Concurrence <br />DATE OF ISSUANCE: 03/28/2022 <br />No. 02 <br />EFFECTIVE DATE: 03/28/2022 <br />OWNER: Indian River County <br />CONTRACTOR Halley Engineering Contractors, Inc. <br />Project: 66TH AVENUE ROADWAY WIDENING (49TH STREET TO 69TH STREET) <br />OWNER's Project No. IRC -1505 OWNER'S Bid No. 2021018 <br />FM No.: 436379-1-54-01 & 436379-1-54-02 <br />You are directed to make the following changes in the Contract Documents: <br />Description: <br />Proceed with construction of 53`d Street Bridge over Lateral A Canal based on a redesigned set of plans <br />Provided by Indian River County, that widens the 53`d Street Bridge from three (3) proposed travel lanes <br />to five (5) proposed travel lanes. <br />The following terms and conditions related to the approval of the Contractor's proposal have been <br />agreed to by Indian River County (IRC) and Halley Engineering Contractors, Inc. (HEC): <br />• The payment structure for the bridge items listed in Exhibit "A" will be changed to Lump Sum (LS). <br />The lump sum amount for the new pay item was mutually agreed upon. Payment for the new lump <br />sum pay item will be in accordance with the schedule of values attached copy labeled Exhibit "B". <br />• No additional compensation will be provided if the Engineer determines that an overrun to an existing <br />structure pay item not deleted by the Change Order is necessary solely as a result of HEC accepting to <br />proceed with the work as one Lump Sum (LS) amount of $1,867,717.85. <br />• No additional compensation will be provided if the Engineer determines that any incidental structures <br />not discussed herein, but depicted in the new design are needed solely as a result of accepting to <br />proceed with the work as one Lump Sum (LS) amount. This does not include additional costs for any <br />possible utility conflicts encountered during the construction of the new bridge. <br />• HEC will be provided an opportunity to thoroughly review the revised bridge plans and design before <br />they are finalized. After the revised bridge plans and design have been finalized, incorporating/ <br />addressing all HEC's comments, no additional compensation will be provided to HEC for any quantity <br />discrepancies as a result of the revised bridge plans and design. <br />• IRC will accept all responsibility for the removal costs of any "man-made" objects that are <br />encountered during installation of any piers that remain in the original planned locations, consistent <br />to the original terms of the Contract. <br />• HEC will be responsible for any overrun of piling required as a result of the revised bridge plans and <br />design, excluding unforeseen subsurface conditions. Any unforeseen subsurface conditions will be <br />treated in accordance with the original Contract documents. <br />• HEC has not made any modifications to the Maintenance of Traffic and general stipulations included <br />in the contract documents as originally bid as a result of the proposed changes. Any required <br />modifications will be submitted for approval prior to implementation, and the cost shall be the <br />180 <br />