Laserfiche WebLink
EXHIBIT C <br />TIME SCHEDULE <br />Task 1 Modeling Approach Memorandum <br />Task 2 Coordination with SJRWMD <br />Task 3 Groundwater Modeling Evaluation <br />Initial Results <br />Draft Modeling Report <br />Final Modeling Report <br />Task 4 Permit Application <br />Task 5 RAls <br />Task 6 Project Management <br />30 days from Notice to Proceed (NTP) <br />As needed, throughout project <br />60 days from approval of memorandum <br />30 days from completion of initial results <br />30 days from receipt of final comments <br />Within 180 days of NTP <br />Response within 45 days of receipt <br />Project Duration <br />Page 6 of 6 <br />