service during construction to accommodate the swapping of equipment). SWDD <br />subsequently determined that the LFG system could not be out of service long enough to <br />accommodate construction of the new system, and rather, a new slab would be required to <br />install the new equipment while maintaining the existing operation. This task will be <br />amended to include the structural design of three new concrete slabs for the new blower <br />skid, the dehydration skid, and the new flare. <br />Subtask 2.5 Bidding and Project Management <br />This task has been amended to provide for additional project management and <br />coordination efforts. <br />Subtask 2.6 Permitting <br />No changes. <br />Task 3: SCADA Coordination and Electrical Considerations <br />No changes. <br />Page 3 of 6 <br />