Page 5 of 8 <br />VII. Federal Aid Participation <br />Time: Zero (0) Days <br />Cost: $0.00 <br />❑ Participating ® Non -Participating <br />William R. Adams III, P.E. — Sr. Project Engineer Date <br />Attachments <br />• Exhibit A: Contractor's Notice of Delay for 54" Storm Pipe — Soil Settlement Impacts dated April 26, 2022 <br />(29 pages) <br />• Exhibit B: Contractor's Request for Time and Compensation dated June 11, 2022 (6 pages) <br />• Exhibit C: Engineer's Time Impact Analysis for 54" Storm Pipe — Soil Settlement Impacts (7 Pages) <br />• Exhibit D: Engineer's Cost Estimate (8 pages) <br />• Exhibit E: Engineer's Work Records (45 pages) <br />• Exhibit F: Contractor's Revised Pricing based on Actuals dated August 25, 2022 (3 pages) <br />• Exhibit G: Email correspondence dated June 24, 2022 (2 pages) <br />• Exhibit H: MOT Developmental Specification Section 173 (6 pages) <br />