Cnnrlusinn <br />Comparing the earliest schedule completion dates of the impacted schedule and un -impacted schedule <br />indicates there is a change in the completion date. <br />CPM Analysis: <br />Data Date Completion Date <br />Un -impacted April 30, 2022 October 6, 2022 <br />Impacted July 27, 2022 January 5, 2023 <br />Difference 91 <br />During the impact period associated with the 54" Pipe Issues and Soil Injection (April 30, 2022, until <br />August 1, 2022), a total of 7 weather days and holidays were granted. In addition, by inspection, it <br />appears there are an additional 4 days (April 27, 2022 to April 30, 2022) prior to the data date of the un- <br />impacted schedule during which the project was also impacted with 1 of those days being a weather <br />day. Therefore, a time extension is warranted for the 54" Pipe Issues and Soil Injection for a total of 87 <br />Calendar Days. <br />229 <br />