- April 26, 2022 - Claim by TRC dated April 26, 2022 <br />- April 27, 2022 - GPR testing was performed by Geoview. <br />May 11, 2022 GPR report date <br />- May 12, 2022 to May 18, 2022 - TRC provided Trunk Line Videos to FDOT <br />May 18, 2022 - Rich received the GPR report? And an e-mail/ voice message from James Hughes <br />May 26, 2022 -Team Meeting with FDOT, where it was requested that IRC gets a cost estimate <br />for poly injections for voids and joints <br />- June 2, 2022 - Rich sends cost estimate for joint repair and void filling to FDOT for an estimate <br />from Uretek of $395,000.00 <br />- June 7, 2022 - Diego send an email authorizing the void filling for $187,000.00 <br />- June 11, 2022 - Bill Adams spoke to Deb Ishan (District 4) <br />- June 11, 2022 -TRC sends proposal for $444,045.07 <br />- June 17, 2022 - Diego and ChloAnn requested a meeting to discuss the proposal from TRC - We <br />agreed on separating the injection work as a WCD and proceed with the time extension with a <br />change order at a later date when exact time required would be known. <br />- June 20, 2022 - WCD 023 was send to FDOT for concurrence ($273,203.51) <br />- June 21, 2022 - CloAnn notified Consor about a disagreement about the Vac truck and the CCTV, <br />and a request to add an FDOT spec to the WCD <br />- June 23, 2022 -James Hughes has signed WCD 023 for $273,203.51. <br />- June 24, 2022 - WCD executed for $273,203.51 <br />- July 18, 2022 - Subcontractor mobilizes to the project <br />- July 27, 2022 - Subcontractor completes the soil injection <br />- August 1, 2022 -TRC remobilizes crews to the project <br />Scope of Analysis <br />This Time Extension Analysis is a retrospective (backward looking) analysis of the impact to the schedule <br />completion date caused by impacts of the 54" pipe issues and associated soil injection work. <br />Description of Analysis <br />The schedule used as a base for the analysis is the April 30, 2022, completion schedule update. This <br />update was chosen because it was the closest update to the start date of the delay event. Although the <br />project was technically being impacted by the 54" pipe issues on April 30, in the interest of efficiency, it <br />was chosen as the "un -impacted" schedule with a completion date of October 6, 2022. <br />For the impacted schedule, activity IM010 was added to the schedule to represent the 54" pipe issues <br />and soil injection collectively (start date of April 25, 2022 and finish date of July 27, 2022) ,and activity <br />IM020 was added to represent the remobilization of the Contractor crews (planned start date of July 28, <br />2022, and planned finish date of August 1, 2022). With a data date of July 27, 2022, the completion date <br />of the impacted schedule is January 5, 2023. <br />228 <br />