Mr. Himanshu Mehta, P. E. <br />28 March 2023 <br />Page 6 <br />the County's Purchasing Division a complete package of the RFB for uploading onto the <br />Demandstar website. SWDD will provide the front-end documents prepared for Phase 1 to be <br />modified by Geosyntec for incorporation into the RFB package. <br />Geosyntec will attend the pre-bid meeting with potential contractors to describe the Project and <br />its requirements and answer questions at the pre-bid meeting. During the bidding process, <br />Geosyntec will respond to written questions by issuing addenda. Preparation of addenda may <br />require revisions to the Construction Drawings or material quantities as necessary to allow <br />comparison and evaluation of bids from the contractors. Geosyntec will manage the procurement <br />process, review and evaluate the bids submitted in compliance with the requirements of the RFB <br />process, and prepare a recommendation with supporting rational for the selection of the preferred <br />candidate contractor for construction of Phase 2 of the Project. <br />SCHEDULE <br />Geosyntec has prepared a schedule for construction contract procurement of the Segment 3 <br />Expansion, which is included as Exhibit B. The schedule, as presented, assumes a start date of 4 <br />April 2023. The first two months will be used to complete the Phase 3 Construction Drawings and <br />other Construction Documents described above. Geosyntec assumes that the bid package will be <br />completed and ready for posting by 15 June 2023. Geosyntec has assumed that the procurement <br />phase including obtaining Board authorization will extend over a period of two to three months <br />leading to the selection of the construction contractor by 15 October 2023. <br />Geosyntec recognizes the importance of the schedule for SWDD and their need to obtain the <br />required disposal capacity from Cell 3 of Segment 3 Expansion of the Class I landfill. Throughout <br />the duration of the Project, Geosyntec will work diligently to meet those milestones and the <br />schedule developed for the Project. <br />BUDGET ESTIMATE <br />Geosyntec proposes to perform the above -referenced work on a lump sum basis for $139,129.70. A <br />budget estimate for the scope of work outlined in Phases 1 through 4 of this proposal is summarized <br />in the following table, and a detailed budget estimate is provided as Exhibit C. <br />Phase 1: General Consulting/Meeting Support/Project Management $31,027.98 <br />Phase 2: Review of Background Documents $22,898.44 <br />Phase 3: Preparation of Construction Documents $56,928.16 <br />Phase 4: Contractor Procurement Services $28,275.12 <br />TOTAL $139,129.70 <br />NCP23230921iL23017 Ce113 Liner Contractor Procurement <br />engnuee i -s i scientists 1 innovators <br />