11 <br />(UGC01153.FMT)aa <br />r <br />S C IO 1. 53 <br />CHANGE ORDER PROCEDURES <br />PART 1 - <br />GENERAL <br />1,01 <br />REQUIREMENTS INCLUDE <br />A. Promptly implement change order procedures.. <br />1. Provide full written data required to evaluate <br />changes. <br />2. Maintain detailed records of work done on a <br />time-and-material/force account basis. <br />3. Provide full documentation to Engineer on <br />request. <br />B. Designate in writing the member of Contractor's <br />organization: <br />1. Who is authorized to accept changes in the <br />work. <br />2. Who is responsible for informing others in the <br />Contractor's employ of the authorization of <br />changes in the work. <br />C. Owner will designate in writing the person who is <br />authorized to execute Change orders. <br />1.02 <br />RELATED REQUIREMENTS <br />A. The amount of established unit prices. <br />B. conditions of the Contract: <br />1. Methods of determining cost or credit to owner <br />resulting from changes in Work made on a time <br />and materials basis. <br />2. Contractor's claims for additional costs. <br />C. Section 01152: Applications for payment. <br />- <br />D. Section 01310: Construction schedules. <br />E. Section 01370: Schedule of Values. <br />F. Section 01720: Project Record Documents. <br />1,03 <br />DEFINITIONS <br />A. Change order: see General Conditions <br />I. <br />01153�x <br />