C-1 <br />40 <br />1.04 PRELIMINARY PROCEDURES <br />A. owner or Engineer may initiate changes by <br />submitting a proposal Request to Contractor. <br />Request will include the following: <br />1. Detailed description of the Change, Products, <br />and location of the change in the Project. <br />2. supplementary or revised Drawings and <br />Specifications. <br />3. The projected time span for making the change, <br />and a specific statement as to whether <br />overtime work is, or is not, authorized. <br />4. A specific period of time during which the <br />requested price will be considered valid. <br />5. Such request is for information only, and is <br />not an instruction to execute the changes, nor <br />to stop work in progress. <br />B. Contractor may initiate changes by submitting a <br />written notice to Engineer, containing: <br />1. Description of the proposed changes. <br />2. Statement of the reason for making the <br />changes, <br />3. Statement of the effect on the Contract Sum <br />and the Contract Time. <br />4. Statement of the effect on the work of <br />separate contractors. <br />5. Documentation supporting any- changes in <br />Contract Sum or Contract Time, as appropriate. <br />1.05 CONSTRUCTION CHANGE AUTHORIZATION <br />A. In lieu of Proposal Request, Engineer may issue a <br />"Work Directive Change" for Contractor to proceed <br />with a change for subsequent inclusion in a Change <br />Order. <br />B. Authorization will describe changes in the work, <br />boLi,t additloi"s and deletions, with attachments of <br />revised Contract Documents to define details of the <br />change. <br />C. Owner and Engineer will sign and date the Work <br />Directive Change as authorization for the <br />Contractor to proceed with the changes. <br />1.06 DOCUMENTATION OF ]PROPOSALS AND CLAIMS <br />A. Support each quotation for a lump sum proposal, and <br />0115]-2 <br />