The acceptance by the Contractor of final payment shall be and shall operate as a release to the Owner from all
<br />claims and all liability to the Contractor other than claims in stated amounts as may be specifically excepted by the
<br />Contractor for all things done or furnished in connection with the work under this Agreement and for every act and
<br />neglect of the Owner and others relating to or arising out of the work. Any payment, however, final or otherwise,
<br />shall not release the Contractor or its sureties from any obligations under this Agreement, or the Invitation to Bid.
<br />5.04 Monthly Statements
<br />The Contractor shall electronically provide the IS&T Division Manager with a monthly account statement. Account
<br />statements shall contain a detailed listing of all invoices presented to the Owner with an indication of the status
<br />(paid or unpaid) of each invoice.
<br />ARTICLE 6 - INDEMNIFICATION
<br />6.01 Contractor shall indemnify and hold harmless the Owner, and its officers and employees, from liabilities,
<br />damages, losses and costs, including, but not limited to, reasonable attorney's fees, to the extent caused by
<br />the negligence, recklessness, or intentional wrongful misconduct of the Contractor and persons
<br />employed or utilized by the Contractor in the performance of the Work.
<br />ARTICLE 7 - CONTRACTOR'S REPRESENTATIONS
<br />7.01 In order to induce Owner to enter into this Agreement, Contractor makes the following representations:
<br />A. Contractor has examined and carefully studied the Contract Documents and the other related data identified
<br />in the Invitation to Bid documents.
<br />B. Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and Site
<br />conditions that may affect cost, progress, and performance of the Work.
<br />C. Contractor is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may
<br />affect cost, progress, and performance of the Work.
<br />D. Contractor has obtained and carefully studied (or assumes responsibility for having done so) all additional
<br />or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions
<br />(surface, subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost,
<br />progress, or performance of the Work or which relate to any aspect of the means, methods, techniques,
<br />sequences, and procedures of construction to be employed by Contractor, including applying the specific
<br />means, methods, techniques, sequences, and procedures of construction, if any, expressly required by the
<br />Contract Documents to be employed by Contractor, and safety precautions and programs incident thereto.
<br />E. Contractor does not consider that any further examinations, investigations, explorations, tests, studies, or
<br />data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in
<br />accordance with the other terms and conditions of the Contract Documents.
<br />F. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that
<br />relates to the Work as indicated in the Contract Documents.